initiation of pilot testing, a request was made to Mr. Lee Slezak <strong>for</strong> his agreement not to engage in the<br />

open house <strong>for</strong> the instrumented truck as originally planned. Several alternatives to conducting the “open<br />

house” were suggested including a suggestion to display the Dana Technology <strong>Truck</strong> outfitted with Pilot<br />

Test data instrumentation at the SAE Government-Industry Meeting in the Washington DC area in May<br />

2006.<br />

Figure 28: Trailer Ballast From Mid-<br />

Trailer to Nose of Trailer<br />

Figure 30: VBOXII Prior to the Loading<br />

of the Ballast<br />

Figure 29: Trailer Ballast From Rear to<br />

Nose of Trailer<br />

Figure 31: WXT510 Weather Station<br />

Mounted on Side Mirror<br />

Pilot Testing took place from October 23, 2005 through January 19, 2006. This period of time<br />

included the holidays and involved considerable bad weather that caused some additional delays.<br />

The map in Figure 32 shows the East-West route, and Figures 33 and 34 show the North-South<br />

route (the route traveling South, and the route traveling North respectively). Each route was<br />

traveled twice (once with standard dual tires and once with new-generation single tires). It<br />

should be noted that the routes taken were not strictly identical, but were very similar.<br />

Two Chicago-to-Portland roundtrip runs were made between October 23, 2005 and November<br />

19, 2005. For the first dataset (collected during the period October 23 rd - November 2 nd 2005),<br />

the truck was mounted with regular dual tires; <strong>for</strong> the second (November 7 th – November 18 th<br />

2005) it had new generation singles. During the two round trips 8,500 miles were covered and<br />

220 hours of driving were logged. More than 24 Gigabits of data were collected and saved to<br />

A-23