Namibia PDNA 2009 - GFDRR
Namibia PDNA 2009 - GFDRR
Namibia PDNA 2009 - GFDRR
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
3.1.3<br />
Energy<br />
In the northern Regions, the damage to electricity infrastructure as a result of the floods and storms which occurred in <strong>2009</strong> was not<br />
extensive compared to that normally sustained during floods, cyclones and other natural disasters. It is important to note however,<br />
that it is highly probable that the lifespan of certain equipment may have been shortened by the effects of the flood. It is extremely<br />
likely that the insulation of certain equipment has been damaged to a limited extent and that this damage will result in early failure. It<br />
is thus necessary to make provision for the replacement of such equipment within a shorter period than normal. In the rural areas,<br />
the utility could not relate cost of damages to specific locations due to the lack of an effective management information system. The<br />
Table below outlines the damage and losses incurred in the energy sector.<br />
Energy company<br />
Table 14: Damage and losses incurred in the energy sector<br />
Damage<br />
(N$ million)<br />
Losses<br />
(N$ million)<br />
Damage<br />
(US$ million)<br />
NORED/OPE 8.7 1.3 1.1 0.2<br />
Losses<br />
(US$ million)<br />
Source: Estimations by <strong>PDNA</strong> Team<br />
The generation and transmission infrastructure of Nampower did not suffer any damage. Damages were limited to distribution<br />
infrastructure. The North Regional Electricity Distributor (NORED) and the Oshakati Premier Electric (OPE) were the only utilities<br />
to suffer damages. In the Caprivi and Kavango Regions, electrical equipment did not incur any damage as a result of flooding asthe<br />
reticulation network is overhead. Lightning strikes were the main cause of failure of small transformers and destruction of wooden<br />
poles. The utility could not provide specific data on location of lightning strikes.<br />
Losses are the revenue lost by the distribution utilities as a result of the disaster. In the northernR, sales of electricity rebounded<br />
extremely rapidly and in most areas March <strong>2009</strong> sales compared favourably with the average of the previous 12 months. This was<br />
due to the restoration of supply to most areas in a short period of time. In the north-eastern Regions, fewer customers were<br />
disconnected and all have been reconnected with the exception of Mabusha Clinic and Sarasunga Lodge in Kavango and Mukusi River<br />
Lodge in the Caprivi which were still without electricity at the time of this assessment.<br />
Needs<br />
The main areas of need with respect to mitigation of risk against further<br />
flood damage are the towns of Ondangwa and Oshakati. These are the areas<br />
with underground systems and a programme needs to be implemented to<br />
raise the mounting levels of equipment as a matter of urgency. There needs,<br />
however, to be a general revision of standards but this applies to the whole<br />
area under the jurisdiction of NORED and OPE.<br />
A general study needs to be undertaken to examine measures which can<br />
be implemented to limit damage by lightning strikes related to conditions<br />
caused by the long MV line lengths throughout the northern <strong>Namibia</strong>n<br />
region.<br />
Figure 19: Flooding in a local village<br />
OPE and NORED commenced reconstruction of the network as soon as it was possible to gain access to the affected areas. Both<br />
OPE and NORED were able to make use of existing stocks of equipment. Temporary supply cables were connected to restore<br />
supply to customers in Ondangwa. The permanent network is currently being reconstructed.<br />
Connections to rural customers in Omusati, Ohangwena, Oshana and Oshikoto and clinics and lodges in Kavango and Caprivi were<br />
restored once the premises were accessible. However, there is a possibility that the lodges may relocate due to extensive flood<br />
damage and potential risk of future flooding.<br />
Reconstruction costs have been financed by the utilities themselves. While the reconstruction process in this sector is almost complete,<br />
attention needs to be paid to developing programmes to mitigate risk of possible damage by similar natural occurrences.<br />
17