Stormwater management, in urban areas, requires a comprehensive solution. Flood water from outside the towns should be diverted before<br />
causing disruption to township. However, rain water and over-spilling water from the outskirts of townships should be carried away by<br />
stormwater systems to be constructed as part of the urban road system. In this regard, proposals from the towns, Oshakati and Ondangwa,<br />
to improve the stormwater management system and construction of critical bridges and roads are included in the needs assessment. 28<br />
Table 46: Urban roads improvements and rain stormwater management<br />
Activity<br />
Cost Estimate<br />
(N$ million)<br />
Ondangwa Town Council stormwater management and roads improvement 29.5<br />
Oshakati Town council stormwater management 107.0<br />
Total 136.5<br />
Total needs: In total, the financing needs for reconstruction and mitigation (making the roads in these areas flood resilient), without<br />
provision for inflation, are in the amount of N$2.8 billion.<br />
The proposed investments suggestion could be aligned with Programme 1 of the transport sector in NDP3 where 2,000 km of rural<br />
gravel roads are proposed to be constructed, 300 km of rural access roads improved to bitumen standards and 1,200 km of trunk<br />
and main roads improved to bitumen. However, they will be on top of NDP3’s investments.<br />
NDP3 is suggesting to upgrade and to construct more roads compared to <strong>PDNA</strong> for obvious reason, since the NDP3 covers all the<br />
country. And this shows that there is a capacity to implement the roads suggested to upgrade and construct by the <strong>PDNA</strong>.<br />
The <strong>PDNA</strong> suggestion is to upgrade 262 km main roads and 450 km rural (district) roads to bitumen standard and improve about 426 km<br />
rural (district) roads. Some of the rural (district) roads when upgraded will move to main road. The roads identified by the <strong>PDNA</strong> could<br />
thus help to determine the category of roads to be upgraded under NDP3. The <strong>PDNA</strong> also suggests constructing about 600 km access<br />
roads while NDP3 anticipates 2000 km and this shows the 600 km access roads could be constructed within the NDP3 framework.<br />
The construction industry has the benefit of tapping into the well developed capacity in neighbouring countries. In addition, it gives<br />
the opportunity for the development of the local construction industry.<br />
Preventive maintenance measures are an important factor in reducing damage and it is also essential to develop a maintenance<br />
strategy that will help to cope with the changes. It is also worth assessing the impacts of such incidences on maintenance cycles and<br />
road life maintenance costs, in order to develop and plan appropriate improvements.<br />
The use of water transport in areas like the Caprivi Region, particularly during the flooding period, is an idea that strongly recommended<br />
by the local population. No damage was observed or reported on the existing telecom towers and ground cables. In most cases the<br />
towers were located on higher ground and the main problem was gaining access for maintenance purposes. Since the ground cable cover<br />
was made of water resistant material, the draining of manholes has continued with little difficulty. The operators have not reported loss in<br />
revenue associated to the flooding. Therefore, this report does not contain a damage and loss estimate for the telecom sector.<br />
However, towers in some places (e.g. Onesi town) were built on outlets of culverts and verges of flood pans, which is an issue to be<br />
considered by the operators before future rainy seasons.<br />
Postal services were also not affected by the flooding and no damage or loss was reported.<br />
28 An additional factor to consider is that stormwater management in urban areas is also related to flooding of houses and other buildings. A<br />
long-term plan to address this issue is likely to significantly increase the needs estimated here.<br />