FY 20<strong>12</strong>-2021 Capital Improvement Plan<br />

Capital Project Expenses Detail<br />

2060 - Parks Construction Category: 20%<br />

Project: 70541 - Parks Capital Equipment (R) Funding Source:<br />

General Obligation Bonds<br />

Project Description:<br />

Purchase new and replace old, outdated equipment such as mowers, trailers, utility vehicles, ball field<br />

preparation machines and pick-up trucks that have outlasted their effective life span for use at parks and<br />

maintenance <strong>of</strong> <strong>city</strong> green spaces and grounds.<br />

Capital Costs: FY 20<strong>12</strong> FY 2013 FY 2014 FY 2015 FY 2016 FYs 17-21<br />

Finance Charges $0 $0 $0 $0 $0 $<strong>12</strong>,500<br />

Equipment $0 $0 $0 $0 $0 $487,500<br />

Sub-Total New Funding $0<br />

$0 $0 $0 $0 $500,000<br />

FY 20<strong>12</strong> Carryover<br />

$22,810 $0 $0 $0 $0 $0<br />

TOTAL $22,810 $0 $0 $0 $0 $500,000<br />

Operating Description:<br />

PC/Vehicle Replacement includes maintenance for 5 mowers, 5 trailers, 5 ball field prep. machines and 2 pickup<br />

trucks. Equipment maintenance is $75 per hour x 20 (# <strong>of</strong> visits) x pieces <strong>of</strong> equipment. Two pick up trucks at<br />

$2,050, $.17 per mile for maintenance costs x 8,000 miles, and $.22 per mile x 8,000 miles for fuel costs. The<br />

remaining equipment will calculated as the equivalent as one vehicle, which is one truck at $2,050, $.17 per mile<br />

for maintenance costs x 8,000 miles, and $.22 per mile x 8,000 miles for fuel costs. A supplemental <strong>budget</strong><br />

request will be submitted once the project is near completion.<br />

Operating Costs: FY 20<strong>12</strong> FY 2013 FY 2014 FY 2015 FY 2016 FYs 17-21<br />

Equip. Maint. $0 $0 $0 $0 $0 $138,482<br />

PC/Vehicle Replacement $0 $0 $0 $0 $0 $<strong>12</strong>7,280<br />

TOTAL $0 $0 $0 $0 $0 $265,762<br />

Project: 70542 - Parks Master Plan Update (R) Funding Source:<br />

General Obligation Bonds<br />

Project Description:<br />

The <strong>city</strong> seeks an updated Parks and Recreation Master Plan document that is concise, performance<br />

measurement based, user friendly and visionary with regards to the health and vibrancy <strong>of</strong> the <strong>city</strong>, its<br />

commercial areas and its neighborhoods. The scheduled update is required to meet agency accreditation<br />

standards.<br />

Capital Costs: FY 20<strong>12</strong> FY 2013 FY 2014 FY 2015 FY 2016 FYs 17-21<br />

FY 20<strong>12</strong> Carryover<br />

$10,177 $0 $0 $0 $0 $0<br />

TOTAL $10,177 $0 $0 $0 $0 $0<br />

Operating Description:<br />

No additional O and M is needed.<br />

* New Project<br />

N=New Asset, R=Replacement <strong>of</strong> Existing Asset, I=Improvement <strong>of</strong> Existing Asset<br />

336<br />