2P Pg. 1 of 3<br />

iemens Proposal #SD22007, CR3 Turbine Generator Retrofit 5/3/07 Review Meeting<br />

n Items Continued:<br />

Siemens to provide proposal amendment letter by 05/18/07.<br />

Siemens to provide 1200 MVA generator component evaluation by 06/08/07.<br />

Siemens to address project schedule:<br />

Generator field installation schedule is 69 days, including 48 days for generator stator winding and core iron<br />

replacement working 24 x 7. Siemens to review generator schedule to identify a ten day reduction. If<br />

generator outage schedule does not fit inside revised plant steam generator replacement schedule, then<br />

evaluate stator midsection replacement. Siemens mentioned the possibility of a seed stator frame becoming<br />

available.<br />

0<br />

Siemens to include the following io the proposal at current price point:<br />

1. Generator main lead bushing replacement.<br />

2. Replace generator H2 seal rings and seal strips on H2 gland, bearing oil catcher and outer oil seal.<br />

3. Generator Ventilation Testing. Add description of requirements.<br />

4. Complete rotor lrain center he<br />

laser alignment and generator fiame foot loading alignment.<br />

5. Replacement of the HP turbine gland steam spillover control valve with larger capacity valve.<br />

6. Machining of the HP turbine steam lead inlet flanges for flexitalic gasket modification.<br />

7. Rebabbit HP turbine and generator bearings due to new rotor journals.<br />

8. New style LP turbine lead free rupture discs.<br />

9. Lowering of the generator leads box to clean and pump sealing groove.<br />

10. A complete new technical manual for the turbine generator (excluding the AEH controller volumes)<br />

and electronic spare parts catalog.<br />

11. Material to support lube oil flush.<br />

12. Seal oil skid modifications to support 75psi generator H2 pressure.<br />

13. The Generator Neutral Transformer will be included in the Siemens electrical evaluation for<br />

1200MVA generator short circuit conditions. Generator protective relay set points will be provided.<br />

14. All LP cylinder alignment and installation features (material and modifications) to install new turbines<br />

are included in proposal.<br />

15. All HP turbine cylinder steam seal surfaces will be checked and machined as necessary.<br />

16. The Generator Neutral Transformer Will be included in the Siemens electrical evaluation for<br />

1200MVA generator short circuit conditions. Generator protective relay set points will also be<br />

provided.<br />

17. AI1 LP cylinder alignment and insrallation features (material and modifications) to install new turbines<br />

are included in proposal.<br />

18. All HP turbine cylinder steam seal surfaces wil be checked and machined as necessary.<br />

Siemens to review the following conceptsrisues:<br />

Project Mananement: PE desires “turnkey” project management with minimal PE support responsibilities.<br />

Siemens to provide millwrights, riggers, welders, pipe fitters, crane operators and winders. TEI may provide<br />

the craft to install the MSRs. Siemens overall project management to include control of additional support<br />

provided by PE (mechanics, electricians, I&C, Mold, insulators, pipe fitters, health physics, laborers,<br />

space attendants, fire watch, etc.). This will eliminate any delays due to ‘‘support requirements by<br />

to discuss this concept with their contracts personnel and provide their position.<br />