02.06.2014 Views

siemens - Public Service Commission

siemens - Public Service Commission

siemens - Public Service Commission

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Attachment A to Request No. KS12007<br />

Certain bidders have asked the following questions in regards to RFP No. KS12007, so this addendum is<br />

in answer to those questions and available to all bidders. A question and answer format has been used.<br />

Turbine building structural evaluation commentslclarifications:<br />

Question: Sections 1.2.13 and 1.9.15 discuss "Conduct an evaluation of the Turbine Building structure<br />

considering the expected additional loads resulting from installation of new and larger equipment"<br />

and "Perform an evaluation of the Turbine Building structure and supports to identify if any significant<br />

changes are required to accommodate the expected increases in loads resulting from new and larger<br />

equipment such as turbine motors, main generator, etc.". Both statements imply there is an evaluation<br />

for the existing building loads. What calculations cover the existing TB evaluations, and will these be<br />

made available?<br />

Answer: Original calculations are Gilbert Commonwealth structural calculations and will be made<br />

available. Estimate 200 hours to review and revise calculations as necessary.<br />

Question: The statements in sections 1.2.13 and 1.9.15 ask for an evaluation to see if significant<br />

changes are required. Please define the term "significant" changes versus others?<br />

Answer: "Significant changes" in design loads would be those that would not meet current acceptance<br />

criteria and would require modifications to the existing floor or support columns.<br />

Question: There is no mention of what to do when changes are required. When changes are required,<br />

are they included with this scope or handled separately outside of this scope?<br />

Answer: The modifications would be scope addition and would be priced separately as T&M, if required<br />

Question: Section 1.12 discusses the schedule for the Turbine Building evaluation (Item 15) and is<br />

scheduled to be completed 12/13/07. It is noted that a PO will not be submitted to anyone before late<br />

August. Before the TB evaluation can be done, inputs for the weights and footprints of all equipment<br />

must be known. This includes major components such as the turbine and MSRs. When will the detailed<br />

vendor information be available and the locations within the TB be defined? The schedule indicates that<br />

equipment information will not be known until after the deadline for the TB evaluation, which would<br />

invalidate the TB evaluation schedule. It appears the schedule needs to be reworked to define<br />

predecessor activities for all tasks.<br />

Answer: The weights of the replacement components are readily available and will be provided as part of<br />

the Owners deliverables within the schedule.<br />

Electrical commentslclarifications:<br />

Question: Section 1 9 5 asks for the complete replacement of the existing system with the 2 X 100%<br />

new system each with 100% motor/fan and cooling coils. while Section 1 2 1 discusses upgrade cooling<br />

unit to have redundant fadmotor and cooling coils The existing unit can not be upgraded to have<br />

redundant fans Therefore two 100% new units would be required<br />

Is the plant replacing the existing cooling unit with two new 100% redundant units or upgrading the<br />

existing unit with redundant motors to meet the design requirements7<br />

Answer: Is0 phase bus duct coolers should be replaced with 2 X 100% redundant coolers and fans.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!