Schedule Risk:<br />

agreement to h ish such corporate guaranties in the form fiunished with this RFP.<br />

Timely completion of the replacement turbine generator at the Crystal River Unit 3 Site by the fall 2009<br />

refueling outage and implementation of an extended reactor power uprate of 17% during the fall 20 1 1<br />

refueling outage is critical to the success of this project. Therefore, the selected bidder will be asked to place<br />

profit at risk to demonstrate understanding and ownership of the schedule.<br />

Irrevocable Standbv Letter of Credit:<br />

Bidder shall affirm on the proposal form its ability and willingness to finish, in PE's favor, an irrevocable standby<br />

Letter of Credit per the Contract. The Letter of Credit shall remain in full force and effect during the term of the<br />

contract and may be engaged by PE in the event of Bidder's default under any such contract.<br />

Insurance:<br />

Furnish proof of valid insurance per contractual requirements.<br />

Alternate Bid Formats:<br />

A bid based on the rcquircments noted herein is required; however, PE encourages Bidder to propose an alternative bid<br />