Alstom Proposal # SD22007, CR3 EPU Turbine Generator Retrofit MeetinP Notes, 05/15/07: Pg. 2 of 7<br />

General Notes:<br />

0 HP Turbine and Generator must be opened in 2007 for field measurements. Is open and close cost included?<br />

- Re: Requested Alstom to consider this R&D-cost to them.<br />

0 Evaluate performance of larger 16.8M2 (57”LSB) LP Turbine.<br />

.Re: - Alstom presented performance curve for 47” and 57” LSB. 57” performs be<br />

Average benefit of 57” LSB is approximately 3MW/year. Cost is<br />

Canyon and performance was much better than expected.<br />

CONFIDENTIP.!.<br />

In. Hg. Both perform the same above 2.7 In. Hg.<br />

Note: the 57”LSB was installed at Diablo<br />

0 Heat balance indicates low feed water temperature between 2009 and 2011 (pg. 201,207,208). What is plant impact?<br />

- Re: Ted say’s reactor is not affected. Lower feedwater temperature is in Alstom heat balance and would not be corrected for in a plant performance<br />

test. Areva would have to evaluate / model the Alstom heat balance for EPU.<br />

0 PE must verify generator frame 75 psi H2 pressure rating for generator stator rewind.<br />

- Re: This is responsibility of PE. Will need Siemens support to document.<br />

0 Support systems for water cooled stator skid and static excitation system are additional cost.<br />

- Re: Alstom requested to provide requirements. See engineering issues.<br />

Evaluate control room impact for new systems.<br />

- Re: Alstom requested to provide requirements. Pump controls and annunciator inputs.<br />

Scope of Supply Comments:<br />

HP Turbine: 7 stage, full impulse design<br />

0 New nozzle plates are fitted into existing nozzle box. Existing nozzle plates may need destructive removal. Is machining or repairs to the<br />

existing nozzle box included?<br />

- Re: Contingency repairs will be extra scope.<br />

0 New inner and outer glands are provided. New gland seals machined for rotor clearance. Are both inner and outer glands type 405 ss (pg.<br />

19)?<br />

- Re: Alstom stated the HP turbine outer glands are poJ included. Proposal was in error. Inner glands are stainless steel.