Progress Energy Crystal River Unit 3<br />

Request for Proposal for Engineering <strong>Service</strong>s to Upgrade Secondary System<br />

6125f2007<br />

0<br />

0<br />

1.9.13 Electrical Distribution System Calculations<br />

A number of upgrades to the secondary plant will result in an increase in the electrical<br />

load on the CR3 electrical distribution system, The Redundant lsophase Bus Ouct<br />

Cooling System, Circulating Water pump motors, SC pump motors, Feedwater Booster<br />

pump motors, and Condensate pump motors will result in significant load increases on<br />

the electrical distribution system, An analysis of the distribution system is required that<br />

must include new load flow, short circuit, motor starting and protection system<br />

coordination studies. The goal of this calculation revision is lo evaluate the adequacy of<br />

existing power system equipment ratings (auxiliary transformers, load centers, motor<br />

control centers, switchgear, cables, etc) to support the higher system load and identify<br />

required upgrades of the electrical distribution system.<br />

An initial evaluation of the impact of ekpected electric load increases on the Station<br />

Auxiliary Transformer, 4KV buses, circuit breakers, switchgear, and cabling is required<br />

to determine any required equipment replacements.<br />

The calculation revision will ensure that power system sources and components, such<br />

as offsite power, transformers, cables and system protection circuits will either continue<br />

to operate within their designed limits with the load increases expected, or identify<br />

system changes needed to assure the planned reconfiguration will not affect the plant<br />

licensing commitments. This study should be completed 2 years prior to the planned<br />

uprate in 2011 to support procurement of equipment and modification packages as<br />

required.<br />

This calculation revision will update existing CR3 electrical distribution calculations. The<br />

calculations currently utilize €TAP and other computer programs for the analysis as<br />

folfows.<br />

Voltage DroplShort Circuit for AC Electrical System - SKM Software<br />

Non Safety 125 VDC - ETAP Software<br />

The seller must identify any additional calculations that require revision as a result of the<br />

EPU upgrades. Procedure EGR-NGGC-0017, Preparation and Control of Design<br />

Analysis and Calculations, applies to this task.<br />

40<br />

PEF-NCR-02006