10.11.2014 Views

RD&D-Programme 2004 - SKB

RD&D-Programme 2004 - SKB

RD&D-Programme 2004 - SKB

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

SSI points out that <strong>SKB</strong> should give an account of the importance of the backfill for the<br />

long-term protective capability of the repository and what research, development and demonstration<br />

is needed to accumulate sufficient knowledge for the needs of the safety assessment.<br />

Kasam is of the opinion that if the different requirements on the backfill are found to be<br />

incompatible, the function of limiting the swelling of the buffer should be prioritized.<br />

Newfound knowledge since RD&D 2001<br />

Studies of backfill are taking place mainly within the framework of three projects that are being<br />

conducted in the Äspö HRL: The Backfill and Plug Test, Backfilling and Closure of Tunnels<br />

and Rock Caverns, and the Prototype Repository. Separate studies have also been made of the<br />

alternative backfill material Friedton.<br />

The Backfill and Plug Test is a full-scale test of concepts A and C, see Figure 18-1. Installation<br />

of the test was finished at the end of 1999 /18-2/.<br />

In the Backfill and Plug Test, a 28-metre long tunnel section was backfilled and instrumented.<br />

Half of the length of the tunnel was backfilled with a mixture of 30 percent bentonite and<br />

70 percent crushed rock (30/70 mixture). The other half was backfilled with crushed rock<br />

(0/100 mixture) and with bentonite blocks placed nearest the roof. The backfill was applied<br />

and compacted layer by layer with vibrating plates developed and built for this purpose. The<br />

technique with compaction of inclined layers was used in the entire tunnel section from floor to<br />

roof with an inclination angle of about 35 degrees. The backfill was divided up by permeable<br />

mats about every two metres for the purpose of artificially wetting the backfill and permitting a<br />

hydraulic gradient to be applied between the mats for flow testing. The backfill and surrounding<br />

rock were instrumented with about 200 sensors for measurement of water pressure, total<br />

pressure and water content. A concrete tunnel plug with a half-metre thick bentonite O-ring<br />

was installed at the end of the test section.<br />

An evaluation of the installation showed that the equipment and the technique for backfilling<br />

and compaction worked well in terms of both function and obtained density, but needed<br />

improvement in terms of the reliability, durability and safety of the compaction equipment.<br />

Although the dry density of the 30/70 backfill close to the roof and walls was lower than<br />

1,650 kg/m 3 near the rock walls and the roof, it is estimated that the mean dry density was<br />

between 1,650 and 1,700 kg/m 3 . The measured mean dry density of the 0/100 backfill was<br />

2,170 kg/m 3 .<br />

Water saturation of the backfill was started after installation and was predicted to be completed<br />

in the spring of 2003, i.e. after about 3.5 years. In order to speed up the wetting of the<br />

30/70 mixture, salt was added to the water that fed the wetting mats so that a mean salinity of<br />

1.2 percent would be reached after full water saturation. In addition, a water pressure of 500 kPa<br />

was applied to the wetting mats.<br />

The results of the measurements of the water saturation process agreed well with the model<br />

calculations obtained when the model of the unsaturated hydraulic conductivity that had been<br />

calibrated in laboratory experiments was used. However, the hydraulic conductivity used in the<br />

model differs from the one measured in the laboratory on water-saturated samples with constant<br />

gradient in oedometers. This is mainly attributed to the inhomogeneity of the backfill /18-3/, but<br />

may also be due to the difference in experimental technique.<br />

The backfill in the Prototype Repository is very similar to the 30/70 mixture used in the Backfill<br />

and Plug Test. The difference between the materials is that ground sodium-converted calcium<br />

bentonite from Milos has been used instead of the natural sodium bentonite MX-80 /18-4/.<br />

The mean density of the backfill as measured by a density meter was 1,750 kg/m 3 , while the<br />

mean density estimated by dividing the hauled-in quantity of backfill by the available volume<br />

was only 1,630 kg/m 3 . This is presumably due to compaction problems in portions with many<br />

instruments and cables and to lower density near walls and roof.<br />

RD&D-<strong>Programme</strong> <strong>2004</strong> 231

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!