of the NPPs starts, however, long-lived decommissioning waste must also be dealt with. This<br />

requires extra space, separate from Clab, where capacity problems may otherwise arise. That is<br />

why the afore-mentioned extensions of SFR are also planned to contain chambers for interim<br />

storage of long-lived LILW. After interim storage, the waste will be transferred to the special<br />

final repository for other long-lived waste that is planned.<br />

A5.2.3 Extensions at SFR<br />

Disposal of the additional waste types that are planned for at the SFR facility imposes roughly<br />

the same requirements on the facility itself as the operational waste that is disposed of there<br />

today. The extensions are therefore planned to consist of a number of rock caverns, at the same<br />

depth and of the same type as today’s. A “re-licensing” of the entire facility is also planned in<br />

conjunction with the extension, so that the different parts can receive short-lived waste from<br />

both operation and decommissioning. This will enable the facility to be utilized maximally.<br />

Extension is planned to take place in three stages. A total of four rock caverns will be built in the<br />

first stage – two for final disposal of short-lived decommissioning waste, one that can be used<br />

for interim storage of long-lived waste, and one for final disposal of large, odd components from<br />

maintenance and repair of the NPPs. As mentioned above, these chambers are planned to be<br />

put into use no earlier than 2020. In a second stage, 10–20 years later, additional rock caverns<br />

for decommissioning waste will be added. The cavern that is planned to be utilized for interim<br />

storage of long-lived LILW will be emptied when the waste is transferred to the final repository<br />

for other long-lived waste. This cavern can then also be used for deposition of short-lived<br />

decommissioning waste. If needed, additional chambers for operational waste may also be built<br />

in this time perspective.<br />

A5.2.4 Final repository for other long-lived waste<br />

The construction of a final repository for other long-lived waste is planned to start at a stage<br />

when most of the NPPs have been phased out. The facility will thereby be the last one in the<br />

entire nuclear waste programme. According to present-day plans, the repository should stand<br />

ready for deposition in around 2045. Long-lived LILW produced before then will be interimstored<br />

as described above.<br />

Plans for an early safety evaluation as well as supportive research regarding the final repository<br />

for other long-lived waste are described in Chapter 25. Site selection for this facility requires its<br />

own siting process. In order to allow sufficient time for this process, but nevertheless ensure that<br />

it is still relevant when the time comes to build the facility, it should, by <strong>SKB</strong>’s reckoning, be<br />

started some time around 2025–2030. Thus, site selection is an open question today, and neither<br />

co-siting with SFR (but at greater depth) or with the then-existing deep repository, nor siting at<br />

an entirely new site, can be ruled out.<br />

The long-lived LILW that will be disposed of in the facility can be described most simply as<br />

waste in which a large fraction of the radionuclides have half-lives in excess of 30 years. The<br />

sources are both the parts of the NPPs located in or close to the fuel, known as core components,<br />

and Studsvik (own activities and management of waste from industry, medical care and<br />

research). The idea is also to utilize the repository for the short-lived waste that arises when<br />

Clab and the encapsulation plant are decommissioned. The design outlined above includes rock<br />

caverns (similar to those in SFR but at greater depth and with important differences in technical<br />

design) that divide the facility into three parts, corresponding to the three categories of waste to<br />

be disposed of.<br />

RD&D-<strong>Programme</strong> <strong>2004</strong> 403