10.11.2014 Views

RD&D-Programme 2004 - SKB

RD&D-Programme 2004 - SKB

RD&D-Programme 2004 - SKB

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Already in the feasibility study, large areas were found to the west of the Simpevarp Peninsula<br />

that warranted further investigations from a geoscientific point of view. The site investigation<br />

was commenced here with geophysical airborne surveys and other studies so that an area could<br />

be prioritized for drilling. An analysis revealed a number of areas with what could be judged to<br />

be equivalent geological conditions. The Laxemar area just west of Simpevarp was therefore<br />

prioritized due to its proximity to existing facilities on the Simpevarp Peninsula. Adhering to the<br />

principle that the deep repository project should be pursued on a voluntary basis, <strong>SKB</strong> started<br />

negotiations with the many concerned landowners to obtain access to the area. The negotiations<br />

were drawn-out, but were finally more or less completed at the end of 2003. The work could<br />

then start, nearly a year later than originally planned.<br />

The aim is still to complete the current stage of the site investigation for both alternatives,<br />

Simpevarp and Laxemar. After that an evaluation will be made, with the support of the collected<br />

data. Contingent upon the results of the evaluation, the idea is to then carry out a complete<br />

site investigation for one of the alternatives, see Figure 10. If the Simpevarp alternative is<br />

prioritized, the investigations can be concentrated there. If the Laxemar area is chosen instead,<br />

further investigations will be conducted there, and the prospects for a connecting tunnel from<br />

Simpevarp will be explored.<br />

In addition to the choice between the two subareas, a number of site-specific geoscientific<br />

issues were identified as being of particular importance in the Oskarshamn case as well. Table 2<br />

summarizes the current status of these issues, mainly with regard to the Simpevarp area, since it<br />

is there that new borehole data are available.<br />

Table 2. Current status of site-specific key issues identified prior to the start of the site investigation<br />

in the site investigation in Oskarshamn.<br />

Key issue<br />

Size and location of bedrock blocks with<br />

favourable properties at repository depth.<br />

Presence and importance of dykes of<br />

fine-grained granite and fracture zones,<br />

particularly with respect to permeability.<br />

Status<br />

Drilling, in combination with lineament interpretations, show that<br />

the Simpevarp subarea is probably surrounded by deformation<br />

zones of such importance that they constitute boundaries for<br />

a possible repository area. Within the area are lineaments<br />

that can be interpreted as zones of lesser importance. Most of<br />

the fractured formations in the boreholes exhibit relatively low<br />

hydraulic conductivity.<br />

Analyses of data from large areas adjacent to and west of<br />

Simpevarp show that fine-grained granite is evenly distributed.<br />

The dykes of fine-grained granite encountered in the boreholes on<br />

the Simpevarp Peninsula have not exhibited elevated permeability,<br />

compared with the surrounding rock.<br />

A4.3 Facility design<br />

Design is the collective term for activities where requirements, design-basis criteria, technical<br />

solutions and other types of information are collected and processed so that they can eventually<br />

be translated into facility descriptions, function descriptions, engineering drawings and<br />

construction documents.<br />

Prior to the site investigation phase, the results of the design work to date were compiled into<br />

a comprehensive facility description outlining <strong>SKB</strong>’s general reference design of the deep<br />

repository. The task during the site investigation phase is to produce site-adapted configuration<br />

proposals and plans for detailed characterization and construction for the studied siting<br />

alternatives. The starting point is the general reference design, which is progressively adapted<br />

to the site conditions revealed by the investigations. At the same time, technical solutions for<br />

subsystems and other results delivered by ongoing development work are implemented (see<br />

section A4.4).<br />

RD&D-<strong>Programme</strong> <strong>2004</strong> 389

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!