A4.4 Technology development<br />

Prior to the permit application for the deep repository, the development work should generally<br />

have reached a level such that technical solutions – for subsystems and for the whole deep<br />

repository on the site in question – can be shown to be feasible and to satisfy the crucial safety<br />

and environmental requirements. They must furthermore satisfy reasonable requirements on<br />

efficiency and resource-effectiveness in the execution of the deep repository project.<br />

A complete account of status and programme for technology development is given in<br />

Chapter 10. The following development issues can be said to be particularly important for<br />

the site-adapted configuration of the deep repository that is done during the site investigation<br />

phase (cf Table 3b):<br />

• Rock excavation technology (adaptation and development of methods for excavation,<br />

rock stabilization and sealing).<br />

• Engineering materials (for sealing, stabilization and underground installations).<br />

• Rock properties for deposition areas and deposition holes (criteria, methodology, adaptation).<br />

• Deposition technology (machines, handling procedure).<br />

• Buffer (materials, fabrication, application).<br />

• Backfill and closure of deposition holes, tunnels and boreholes (materials and application).<br />

Figure 12 shows a general plan for the development work, with a time horizon of 2008. As<br />

the figure indicates, the results of the development work find their primary application in the<br />

safety assessment and in the stepwise design process. Table 5 provides an overview of the<br />

current “delivery plan” vis-à-vis the implementation plan for the deep repository project. The<br />

table presents interim goals in the form of preliminary requirements on background material<br />

regarding the formulated issues linked to the different design steps. In addition, brief comments<br />

are made on the development situation with references to those sections in the main report<br />

where the RD&D work is described.<br />

The above development activities pertain to the components in the reference concept, i.e. a<br />

repository according to the KBS-3 method with deposition in vertical holes in the tunnel floor.<br />

To this can be added the special development programme for the variant of KBS-3 where<br />

deposition takes place in long horizontal holes (KBS-3H), which is described in section A2.3.5.<br />

394 RD&D-<strong>Programme</strong> <strong>2004</strong>