10.11.2014 Views

RD&D-Programme 2004 - SKB

RD&D-Programme 2004 - SKB

RD&D-Programme 2004 - SKB

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

When the welding chamber was built, the recommended maximum pressure was 0.5 millibar.<br />

During testing it was found that the pressure had to be less than 0.2 millibar in order for the<br />

welding process to be stable. If the pressure exceeds 0.25 millibar at maximum welding power,<br />

extensive plasma formation occurs in the area around the weld pool. The plasma disturbs the<br />

beam, resulting in poorer weld quality. An additional vacuum pump was installed. Along with<br />

other measures, such as leak detection and sealing of the welding chamber, plus a minor rebuild,<br />

this improved the vacuum level in the welding chamber to about 0.05 millibar.<br />

The beam’s electron distribution has been measured regularly to determine the relationship<br />

between electron distribution and weld quality and to assess the condition of the cathode,<br />

see Figure 6-5.<br />

<strong>Programme</strong><br />

Standard EBW machines are normally reliable. The equipment at the Canister Laboratory is<br />

much more complicated than a standard machine. It is more like a prototype, and its reliability<br />

has therefore been less than desirable. A number of measures are planned during the autumn of<br />

<strong>2004</strong> to improve reliability:<br />

• Develop and improve the manufacture of cathodes. The goal of the work under way at TWI<br />

is enable cathodes to be precision-made so that they generate uniform beams and welding<br />

results at identical parameter settings. It must also be possible to mount the cathodes in the<br />

welding machine without individual adjustment.<br />

• Develop, test and rebuild the high-voltage cable’s connection to the gun to minimize the risk<br />

of flashover.<br />

• Rebuild the beam generation system so that the beam bore in the gun is simplified and the<br />

risk of flashover is minimized. This work is expected to be finished during the autumn of<br />

2005 so that the demonstration series of 20 lid welds is not delayed.<br />

Figure 6-5. Electron density in beam focus. Green indicates low density and violet high density.<br />

RD&D-<strong>Programme</strong> <strong>2004</strong> 69

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!