AN INDEPENDENT <strong>EVALUATION</strong> OF THE LCNF<br />

FlexDGrid<br />

Project Title<br />

FlexDGrid<br />

Tier 2<br />

DNO<br />

WPD<br />

Status Ongoing (March 2017)<br />

LCNF Project funding £13.513m<br />

Project objectives FlexDGrid’s objective is to develop and trial an advanced fault level management solution to improve the utilisation of the 11 kV<br />

networks<br />

Assessment<br />

Criteria<br />

Accelerates the development of a low<br />

carbon energy sector<br />

Score<br />

(1-5)<br />

5<br />

Overview of assessment, sources of evidence and comments<br />

Assessment:<br />

The project clearly facilitates the connection of low carbon generation or demand.<br />

The carbon benefits are credible and quantified.<br />

References:<br />

• Summary of the LCNF funds learning EATL, April 2016<br />

• LCNF Full Submission Pro-Forma<br />

Evidence summary:<br />

Key project objectives:<br />

• Lower cost to connect generation<br />

• Accelerate the time to connect generation<br />

• Reduce CMLs and CIs<br />

• Facilitate the connection of Combined Heat and Power (CHP) generation to enable the supply of<br />

heat in new developments in Birmingham.<br />

The carbon benefits are associated with low carbon generation offsetting carbon generation and the<br />

provision of heat offsetting the direct use of gas in properties.<br />

PÖYRY MANAGEMENT CONSULTING<br />

October 2016<br />

713_Poyry_Report_Evaluation_of_the_LCNF_FINAL_Oct_2016_v700.docx<br />