AN INDEPENDENT <strong>EVALUATION</strong> OF THE LCNF<br />

Has the potential to deliver net<br />

financial benefits to future and/or<br />

existing customers<br />

Has a Direct Impact on the operation<br />

of a DNO’s Distribution System<br />

-<br />

5<br />

the load is higher.<br />

• RTTR of Transformer The pole mounted transformer (PMT) is probably not overloaded in winter<br />

even though the static rating indicates that it is. In summer, despite the load being lower and the<br />

transformer rating being higher than that indicated by the static rating, the transformer was<br />

overloaded.<br />

References:<br />

• Close down report<br />

Assessment:<br />

Evidence that the project is highly likely to deliver financial benefits to the majority of customers, but that<br />

these benefits are comparatively short term (e.g. associated with asset replacement deferment)<br />

The planned DSR trial was not achieved due to a delay in the role out of Smart Meters<br />

If the highest loading is during the coldest times of the year, upgrading a transformer that appears to be<br />

overloaded may not be required. This could save around £8,000 per transformer that is not replaced.<br />

Avoiding transformer upgrades is the main benefit assessed – but would need monitoring of each feeder<br />

to justify this.<br />

References:<br />

• Close down report<br />

Assessment:<br />

Parts of the project are utilised in later LNCF projects<br />

Whilst not yet fully developed, the project has opened up new possibilities for new ways of working to be<br />

developed into a strategy with input from Tier 2 projects so that they can become Business As Usual.<br />

Much of the learning generated from engaging with the village residents in this project has influenced<br />

SPENs ED1 strategy for BaU Community / Stakeholder Engagement.<br />

References:<br />

• Close down report<br />

• Questionnaire response<br />

PÖYRY MANAGEMENT CONSULTING<br />

October 2016<br />

713_Poyry_Report_Evaluation_of_the_LCNF_FINAL_Oct_2016_v700.docx<br />

337

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!