05.02.2017 Views

283757893275

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Structural Concrete Frames 367<br />

Soldiers<br />

to sides<br />

Struts<br />

Formwork for<br />

internal beams<br />

Plywood decking to floor<br />

Bearers<br />

Ledgers on<br />

steel props<br />

Adjustable<br />

steel props<br />

Ply sides and base<br />

to beam formwork<br />

100 × 75 mm<br />

bearers at 300 mm<br />

centres<br />

150 × 75 mm ledgers<br />

19 mm plywood lining<br />

to column formwork<br />

100 × 75 mm<br />

backing members<br />

Adjustable steel<br />

props as falsework<br />

Steel column clamps<br />

Figure 6.15 Formwork and falsework.<br />

Figure 6.17. Falsework consists of adjustable steel props fixed as struts to the sides. Temporary<br />

falsework and formwork are struck and removed once the concrete they support<br />

and contain has developed sufficient strength to be self-supporting. In normal weather<br />

conditions, the minimum period after placing ordinary Portland cement concrete that<br />

formwork can be struck is from 9 to 12 hours for columns, walls and sides of large beams,<br />

11–14 days for the soffit of slabs and 15–21 days for the soffit of beams.<br />

Column formwork<br />

Column formwork can be constructed from short wall panels, with the ends of the panel<br />

overlapping (Figure 6.15, Figure 6.16 and Figure 6.17), or it can be constructed using specially<br />

designed and fabricated column formwork (Figure 6.18, Figure 6.19 and Figure 6.20

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!