Table B-2b<br />
Omaha Suburban Station Estimate<br />
Bus Shelter 5 ft wide 20 ft long Area (ft 2 ) 100 $150 per ft 2<br />
Paving Area 108 ft wide 250 ft long Area (ft 2 ) 27000<br />
Lighting 8 each $2,000 each<br />
Curb and Gutter 800 ft total length $16 per ft<br />
Platform 15 ft wide 200 ft long Area (ft 2 ) 3000 $100 per ft<br />
Asphalt 6 in thick Density 153 lb/ft 3 $45 per ton<br />
Concrete Sidwalk and Pad 200 ft 2 $3 per ft 2<br />
Earthwork 3200 yd 3 $15 per yd 3<br />
Ticket vending machine (TVM) 2 each $65,000 each<br />
Land Acquisition 33750 ft 2 $5 per ft 2<br />
Cost estimate<br />
Assumptions:<br />
Bus Shelter $15,000 Bus Shelter is a standard shelter without special ro<strong>of</strong>ing<br />
Excavation $48,000 Utility Services supplied by local utility companies<br />
Asphalt $47,000 Asphalt is standard City <strong>of</strong> Omaha or <strong>Nebraska</strong> <strong>Department</strong> <strong>of</strong> <strong>Roads</strong> Mix<br />
Concrete Sidwalk and Pad $600 90 parking stalls, 10 ADA parking stalls<br />
Curb and Gutter $13,000 Approximately 27,000 ft 2 <strong>of</strong> asphalt pavement constructed<br />
Signage $2,000 Land Acquisition based average unit price for ROW acquisition<br />
TVM's $130,000 Assume site soils are suitable for building and parking lot construction<br />
Platform $300,000 6" Concrete Class 47B-3000 Surfacing<br />
Exterior Lighting $16,000 2 Ticket Vending Machines<br />
Land Acquisition $169,000<br />
Contingency (30%) $172,000<br />
Engineering (15%) $112,000<br />
Construction (15%) $112,000<br />
$1,136,600