Table B-3b<br />

Omaha Layover Facility Estimate<br />

Building 24 ft wide 24 ft long Area (ft 2 ) 576 $75 per ft 2<br />

Fenced Area 42 ft wide 74 ft long Area (ft 2 ) 3108 $20 per linear ft<br />

Trackwork 700 ft total length $140 per ft<br />

Rail bed sub-ballast Avg. depth (ft) 0.5 Avg. width (ft) 19.5 Area (yd 2 ) 1517 $10 per yd 2<br />

Rail bed Excavation 30 ft wide per spur<br />

Switches 2 each $215,000 per each<br />

Asphalt 6 in thick Density 153 lb/ft 3 $45 per ton<br />

Earthwork 3000 yd 3 $10 per yd 3<br />

Land Acquisition 1999 ft 2 $8 per ft 2<br />

Cost estimate<br />

Omaha Assumptions:<br />

Building (complete) $175,000 Building is pre-fabricated structure with a typical footing design<br />

Excavation $30,000 Building has a basic finished interior<br />

Asphalt $53,000 Utility Services supplied by local utility companies<br />

Curb and Gutter $13,000 Asphalt is standard City <strong>of</strong> Omaha or <strong>Nebraska</strong> <strong>Department</strong> <strong>of</strong> <strong>Roads</strong> Mix<br />

Fencing $5,000 Approximately 92,000 ft 2 <strong>of</strong> asphalt pavement constructed<br />

Exterior Lighting $50,000 Maintenance access to rail is asphalt<br />

Subballast $16,000 Access road is 300 feet long and 24 feet wide without curb<br />

Trackwork $98,000 Automobile pavement will include curb and gutter<br />

Switches $430,000 Fencing is chain link<br />

HEP Power Hook-up $100,000 Trackwork price includes rail, ties, ballast and other track materials<br />

Generator $7,500 Switches are power operated<br />

Property Maintenance Equipment $40,000 Site soils are suitable for building and track construction<br />

Land Acquisition $16,000 Land Acquisition based average unit price for ROW acquisition<br />

Contingency (30%) $311,000 Property Maintenance Equipment will be leased or subcontracted<br />

Engineering (10%) $133,000<br />

Construction (10%) $133,000<br />

$1,610,500