Table B-3a<br />
Lincoln Maintenance Facility Estimate<br />
Building 250 ft wide 500 ft long Area (ft 2 ) 125000 $45 per ft 2<br />
Fenced Area 268 ft wide 550 ft long Area (ft 2 ) 147400 $20 per linear ft<br />
Trackwork 4,400 ft total length $140 per ft<br />
Rail bed sub-ballast Avg. depth (ft) 0.5 Avg. width (ft) 19.5 Area (yd 2 ) 9534 $10 per yd 2<br />
Rail bed Excavation 30 ft wide per spur<br />
Switches 6 each $215,000 per each<br />
Asphalt 6 in thick Density 153 lb/ft 3 $45 per ton<br />
Earthwork 52000 yd 3 $10 per yd 3<br />
Land Acquisition 715275 ft 2 $8 per ft 2<br />
Cost estimate<br />
Lincoln Assumptions:<br />
Building (complete) $175,000 Building is pre-fabricated structure with a typical footing design<br />
Excavation $520,000 Building has a basic finished interior<br />
Asphalt $279,000 Building is wide enough to accommodate three tracks<br />
Curb and Gutter $10,000 Utility Services supplied by local utility companies<br />
Fencing $33,000 Bus Shelters will be 2 MAT standard size shelters<br />
Subballast $96,000 Sidewalk will be constructed at the bus shelter locations<br />
Trackwork $616,000 Asphalt is standard City <strong>of</strong> Omaha or <strong>Nebraska</strong> <strong>Department</strong> <strong>of</strong> <strong>Roads</strong> Mix<br />
Switches $1,290,000 Area inside fence and outside <strong>of</strong> building is asphalt<br />
Shop Machinery $250,000 Maintenance access to rail is asphalt<br />
Generator $7,500 Access road is 300 feet long and 24 feet wide without curb<br />
Electrical (20%) $655,300 Automobile pavement will include curb and gutter<br />
HEP Power Hook-up $100,000 Fencing is chain link<br />
Fueling Facility $50,000 Trackwork price includes rail, ties, ballast and other track materials<br />
Washing Facility $100,000 Switches are power operated<br />
Property Maintenance Equipment $40,000 Assume site soils are suitable for building and track construction<br />
Land Acquisition $5,723,000 Property Maintenance Equipment will be leased or subcontracted<br />
Contingency (30%) $2,984,000 Land Acquisition based average unit price for ROW acquisition<br />
Engineering (10%) $721,000<br />
Construction (10%) $721,000<br />
$14,370,800