CHAPTER 5 – COMMUTER RAIL PLAN<br />
<strong>of</strong> less than 12 axles, and this inability is results in a serious safety issue. The safety implications<br />
are obvious, requiring at least three cars in the train set. Each train set costs $6.8 million, FOB<br />
plant (Fort Lupton, Colorado). The purchase <strong>of</strong> DMUs is assumed to be tax exempt. The total<br />
for all four, accordingly, is $27.2 million. A schematic <strong>of</strong> the three-car train set appears below.<br />
SUMMARY OF CAPITAL COSTS<br />
Total capital costs, inclusive <strong>of</strong> track work, stations, sidings, design and contingencies, are $79<br />
million. The costs appear in Table 5-9 below.<br />
Table 5-9: Estimated Capital Costs<br />
Unit<br />
Description<br />
Unit Price Quantity Amount<br />
136# Rail, Ties, Ballast & OTM Track Mile $740,000 2.6 $1,924,000<br />
6" Sub-ballast SY 6 31,200 187,200<br />
Earthwork/Grading CY 10 65,000 650,000<br />
At-Grade Crossings Each 230,000 0 $0<br />
Centralized Traffic Control Track Mile 100,000 0 $0<br />
#24 Power Operated Switches w/ Signals Each 750,000 14 10,500,000<br />
Railroad Culvert Pipe Each 7,500 0 $0<br />
Railroad Bridges LF 6,500 0 $0<br />
Grade Separations Bridges SF 100 0 $0<br />
Seeding Acre 1,500 21 31,500<br />
Roadway Culvert Pipe Each 2,000 0 $0<br />
Right <strong>of</strong> Way Acre 3,000 0 $0<br />
Wetland Mitigation Acre 15,000 0 $0<br />
Subtotal 13,292,700<br />
Passenger Facilities/Station Improvements 4,581,200<br />
Maintenance and Layover Facilities 15,981,300<br />
Siding Tracks 12,840,650<br />
Misc. Realignments 10% 1,329,270<br />
Misc. Construction & Contingency 20% 2,658,540<br />
Subtotal 50,683,660<br />
Est. Main Line Engineering 8% 1,382,441<br />
Subtotal 52,066,101<br />
Train Sets - 4 @ $6.8 Million Each (no tax) 27,200,000<br />
Total $79,266,101<br />
Source: HWS Consulting<br />
384180<br />
NEBRASKA TRANSIT CORRIDORS STUDY<br />
Page 5 - 13<br />
WILBUR SMITH ASSOCIATES