DSLBD Office Fit Out - Broughton Construction Company
DSLBD Office Fit Out - Broughton Construction Company
DSLBD Office Fit Out - Broughton Construction Company
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
SECTION 09 91 00 - PAINTING<br />
PART 1 - GENERAL<br />
1.01 SUMMARY<br />
A. Work Included:<br />
1. Work required under this section consists of surface preparation, priming, painting, and finishing<br />
work necessary to complete Work indicated or reasonably implied on Drawings.<br />
1.02 SUBMITTALS<br />
A. Product Data:<br />
1. Submit a complete list of products proposed for use, including identifying product names and<br />
catalog numbers.<br />
B. Samples:<br />
1. Submit 2 samples of each color and material selected.<br />
2. Samples shall be submitted on 12" x 12" hardboard and shall be labeled on back, identifying color<br />
name and number, manufacturer, and product name.<br />
1.03 QUALITY ASSURANCE<br />
A. Qualifications:<br />
1. When a product manufacturer is not indicated, provide products from a company specializing in<br />
manufacture with a minimum of 5 years experience.<br />
2. Applicator shall be trained in installation techniques and procedures of painting materials and shall<br />
demonstrate a minimum of 3 years successful experience in such application. Applicator shall<br />
employ, on Project, mechanics with a minimum of 2 years documented experience.<br />
B. Regulatory Requirements:<br />
1. Conform to applicable codes and ordinances for flame, fuel, smoke, and volatile organic compound<br />
(VOC) ratings requirements for finishes at time of application.<br />
1.04 FIELD SAMPLE<br />
A. Requirements:<br />
1. Contractor shall schedule meeting with Architect to review the first finished items. Review shall be<br />
scheduled so as not to impede the progress of the project but shall occur prior to purchase of<br />
materials.<br />
2. The first finished items of each color will be reviewed for color, texture and workmanship.<br />
3. The first acceptable item of each color will be used as the project standard.<br />
4. Field Samples shall be no smaller than 100 sq.ft.. Where two or more colors / finishes adjoin<br />
provide 100 sq. ft. of each. Provide as many adjoining materials as possible; ceiling tile, base,<br />
carpet, etc..<br />
1.05 MAINTENANCE<br />
A. Extra Materials:<br />
1. Provide, in manufacturer's unopened original containers, 1 gallon of each top coat color and store<br />
where directed by Owner. These containers will constitute extra stock for Owner's future<br />
maintenance needs.<br />
2. Label each container with room locations in addition to manufacturer's label.<br />
PAINTING 09 91 00-1