SECTION 01 35 16 - ALTERATION PROJECT PROCEDURES<br />
PART 1 - GENERAL<br />
1.01 SUMMARY<br />
A. Section Includes:<br />
1. Products and installation for patching and extending Work<br />
3. Transitions and adjustments<br />
4. Repair of damaged surfaces, finishes, and cleaning<br />
5. Temporary partitions to allow building occupancy<br />
6. Waste management<br />
1.02 QUALITY ASSURANCE<br />
A. Qualifications:<br />
1. Procedures and administration requirements of this section apply to all sections of specifications<br />
that are involved in alterations to building.<br />
2. Assign work of moving, removal, cutting, patching, and repair to trades so as to cause least<br />
damage to each type of work encountered, and to return building as much as possible to<br />
appearance of new work.<br />
3. Patching of finish materials shall be assigned to mechanics skilled in work of finish trade involved.<br />
1.03 PROJECT CONDITIONS<br />
A. Unforeseen Conditions:<br />
1. Should unforeseen conditions be encountered that affect design or function of Project, investigate<br />
fully and submit an accurate, detailed, written report to Architect.<br />
2. While awaiting Architect’s response, reschedule operations if needed to avoid delay of overall<br />
Project.<br />
1.04 SEQUENCING AND SCHEDULING<br />
A. Work Sequencing:<br />
1. Access to occupied spaces shall be obtained through [Owner] [Building Manager] [Tenant] with a<br />
minimum of 72 hours notification.<br />
2. Work done in occupied spaces shall be left clean and neat, and free from dust accumulations.<br />
3. Jack-hammering, use of power actuator, hammer drilling, and other similar operations creating<br />
noises, odors, or fumes shall not be performed between hours of 8:00 AM and 6:00 PM. All<br />
operations creating conditions as indicated above shall cease sufficiently in advance of 8:00 AM to<br />
allow for clean up as necessary to allow use of spaces by Owner, public, and tenants where<br />
needed.<br />
B. Public Access:<br />
1. Public access to occupied spaces shall be maintained at all times during normal business hours.<br />
Provide protection for work in-place and safety of public during construction.<br />
PART 2 - PRODUCTS<br />
2.01 MATERIALS<br />
A. New Materials:<br />
ALTERATION PROJECT PROCEDURES 01 35 16-1