SECTION 01 20 00 - PRICE and PAYMENT PROCEDURES<br />

PART 1 - GENERAL<br />

1.01 SUMMARY<br />

A. Work Included:<br />

1. Schedule of Values<br />

2. Applications for Payment<br />

3. Change Order Procedures<br />

4. Allowances<br />

5. Alternates<br />

1.02 SCHEDULE OF VALUES<br />

A. Procedures:<br />

1. At least 15 days prior to first Application for Payment, submit to Architect a Schedule of Values<br />

allocated to various portions of Work.<br />

2. Prepare schedule in such form, and supported by such reasonable data to substantiate it. This<br />

schedule, unless objected to by Architect or Owner, shall be used only as a basis for Applications<br />

for Payment.<br />

B. Format:<br />

1. Schedule of Values shall in general follow sequence of sections in Specifications. Identify each line<br />

item with section number and title as listed in Table of Contents of this Project Manual.<br />

2. In addition to line item costs of sections listed, list line item costs for each of following:<br />

a. Performance and Payment Bonds (when applicable)<br />

b. Contractor's fee<br />

c. Field supervision<br />

3. Prorate costs, such as costs of overhead, insurance, taxes, warranties and record drawings,<br />

through life of Contract.<br />

4. Estimated values of each principal category of Work shall, when added together, equal total<br />

Contract Sum.<br />

5. For each line item which has an installed value greater than $20,000, break down costs to list<br />

major products or operations under each item.<br />

1.03 APPLICATIONS FOR PAYMENT<br />

A. Draft Applications:<br />

1. Prepare a draft copy of each application for review.<br />

2. Contractor and Architect shall schedule a "walk-through" of Project and review of draft<br />

approximately 3 days prior to submission of Application for Payment.<br />

3. Modifications and revisions made during review of draft shall be incorporated into Application for<br />

Payment.<br />

B. Format:<br />

1. Form to be used shall be AIA G702 - Application and Certificate for Payment; including continuation<br />

sheets when required.<br />

C. Preparation of Applications:<br />

1. Present required information in a typewritten form or electronic media printout.<br />

2. Execute certification by signature of authorized officer.<br />

3. Stored products may be included upon prior agreement and in accordance with criteria established<br />

by Owner.<br />

PRICE and PAYMENT PROCEDURES 01 20 00-1