11.07.2015 Views

T.F. Green Airport Improvement Program - FEIS Chapters - PVD

T.F. Green Airport Improvement Program - FEIS Chapters - PVD

T.F. Green Airport Improvement Program - FEIS Chapters - PVD

SHOW MORE
SHOW LESS
  • No tags were found...

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

T.F. <strong>Green</strong> <strong>Airport</strong> <strong>Improvement</strong> <strong>Program</strong>Environmental Impact Statement and Final Section 4(f) EvaluationTable 5-131Significant Impacts: Summary Comparison of the Significant Impacts of Alternatives B2 andB4 Prior to Mitigation (continued)PhasingAlternative B2Net Change from No-Action Alternative2015 2020All SafetyEnhancementElements 1All EfficiencyEnhancementElements 2Alternative B4Net Change from No-Action Alternative2015 2020All Safety EnhancementElements andRunway 5-23 Extension 3Remaining EfficiencyEnhancementElements 4Section 4(f)/Section 6(f) Resources 8Noise-sensitive historical None None None Noneresources exposed to noise> DNL 65 dB or recreationalresources exposed to noise> DNL 75 dBEligible <strong>Airport</strong> Historic District — Alter historical Alter historical configuration —configuration of airfield of airfield and removeand remove Hangar Hangar No. 1No. 1; Change in viewsto eligible airport historicdistrict.Hangar No. 1 — Demolish for safety Demolish for safety —Hangar No. 2 — Interior modifications. Interior modifications; no —Change in setting and adverse effectaccessRhode Island State <strong>Airport</strong> — Reduction in views Elimination of public view, —Terminaldirect impact to landscapingWinslow Park 8 — Remove park facilities Remove park facilities —within RPZwithin RPZWetlands and Waterways 2.5 acres, 510 linear feet 3.3 acres, 263 linear feet 5.0 acres, 843 linear feet —Floodplains — 0.5 acres, 233 cubic yards 2.3 acres,726 cubic yards —Note: No significant impacts for the other environmental impact categories: Social and Economic, and Environmental Justice; Surface Transportation; Air Quality; WaterQuality; Fish, Wildlife, and Plants; Federal Threatened and Endangered Species; Coastal Resources; Farmlands; Hazardous Materials and Solid Waste; LightEmissions and Visual Environment; and Natural Resources and Energy Supply.See Table 5-132 for other environmental consequences as identified by the additional impact analyses.1 Elements expected to be completed by the end of 2015 include: Runway 16-34 safety areas; taxiways and aprons; navigational aids and lighting; Runway 16-34Perimeter Road; drainage and utilities; mandatory land acquisition for construction; Delivery Drive relocation; Partially Relocated <strong>Airport</strong> Road, including drainageand utilities and necessary land acquisition; and Hangar No. 1 demolition.2 Elements expected to be completed by 2020 include: Runway 5-23 extension and safety areas; taxiways and aprons; navigational aids and lighting; Runway 5-23Perimeter Road; drainage and utilities; necessary land acquisition; Fully Relocated <strong>Airport</strong> Road, including drainage and utilities and necessary land acquisition;Runway 5-23 and 16-34 reconstruction/repaving; expanded passenger terminal and gates; new GSE facility; new belly cargo facility; new fuel farm; newIntegrated Cargo Facility; expanded auto parking facilities; and reconfigured terminal access roadways.3 Elements expected to be completed by the end of 2015 include: Runway 16-34 safety areas; taxiways and aprons; navigational aids and lighting; Runway 16-34Perimeter Road; drainage and utilities; mandatory land acquisition for construction; Delivery Drive relocation; Partially Relocated <strong>Airport</strong> Road, including drainageand utilities, and mandatory land acquisition for construction; and Hangar No. 1 demolition.4 Elements expected to be completed by the end of 2015 include: Runway 5-23 extension and safety areas; taxiways and aprons; navigational aids and lighting;Runway 5-23 Perimeter Road, including drainage and utilities, and mandatory land acquisition for construction; and Realigned Main Avenue, including drainageand utilities, and mandatory land acquisition for construction.5 Refer to Section 5.3.2.1, Finding: Significant Noise Impacts for an explanation of the differences in noise impacts between Alternative B2 and B4. May includehomes that have already been sound insulated as part of a previous sound insulation effort under the Part 150 NCP.6 Baha’i Faith and John Wickes School have been sound insulated as part of a previous sound insulation effort under the Part 150 NCP.7 Alternatives B2 and B4 both would encroach on WHC 26 (located at the Runway 5 End) resulting in a significant impact to this resource. The boundaries of thisresource have been confirmed through field verification.8 Section 6(f) resources are within Winslow Park.Chapter 5 - Environmental Consequences 5-283 July 2011\\mawatr\ev\09228.00\reports\<strong>FEIS</strong>_Final_July_2011\<strong>PVD</strong>_CH05_Environmental_Cons_JUL_2011.doc

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!