1.14 All the materials to be used/replaced in <strong>maintenance</strong> should be <strong>of</strong> approved<br />

quality and to the satisfaction <strong>of</strong> Engineer-in-charge. The replaced materials shall be<br />

disposed <strong>of</strong>f by the Contractor.<br />

1.15 The Contractor shall not claim <strong>for</strong> sales tax, handling/ transportation charges<br />

<strong>for</strong> the repairing and replacement. This is applicable <strong>for</strong> the equipments,<br />

which is required to be taken out <strong>for</strong> repairing also.<br />

1.0 FORCE MAJEURE: No liability shall be attached to the Contractor <strong>for</strong> nonoperation<br />

or <strong>for</strong> execution <strong>of</strong> his obligation under this tender as a result <strong>of</strong> <strong>for</strong>ce<br />

majeure i.e. earth quake, war, revolts, riots, floods, explosions and civil commotions<br />

or any factor which in opinion <strong>of</strong> Engineer-in-Charge is beyond the control <strong>of</strong> the<br />

Contractor.<br />

2.0 The Contract is <strong>for</strong> a period <strong>of</strong> two years i.e. 24 months, from the date <strong>of</strong> award <strong>of</strong><br />

work. This may be extended further on mutual discussion and agreement. <strong>GAIL</strong><br />

reserves the right to terminate the Contract without assigning any reason during the<br />

currency <strong>of</strong> the Tender period by giving 30 days notice to the Contractor.<br />

3.0 The successful Bidder shall furnish to <strong>GAIL</strong> a per<strong>for</strong>mance bank guarantee (PBG) <strong>for</strong><br />

an amount <strong>of</strong> 10% <strong>of</strong> the total <strong>contract</strong> value. The PBG shall be valid till at least 3<br />

months after the <strong>contract</strong>ual completion period. The PBG shall be furnished within<br />

fifteen (15 days) <strong>of</strong> the issue <strong>of</strong> the Letter <strong>of</strong> Selection, and the same shall be<br />

returned back after three months from the date <strong>of</strong> completion <strong>of</strong> <strong>contract</strong> provided<br />

all the bills are cleared and settled and no dispute is recorded. If the BG is not<br />

submitted, the amount shall be adjusted against the first RA bill <strong>of</strong> the Contractor.<br />

The rates quoted by the <strong>contract</strong>or shall be inclusive <strong>of</strong> all statutory taxes including<br />

service tax and duties, statutory taxes and duties like TDS, WCT etc. shall be<br />

recovered from the <strong>contract</strong>or’s bill as per rules. The rates quoted by the<br />

<strong>contract</strong>or shall be firm and shall be applicable during the currency <strong>of</strong> the <strong>contract</strong>.<br />

For Split/Window ACs/Water Coolers/Refrigerators etc :<br />

1.19 The <strong>contract</strong>or should check all Windows/Split ACs, Water Coolers, Refrigerators,<br />

etc be<strong>for</strong>e taking over the equipments from <strong>GAIL</strong>. If there are deficiencies found in<br />

the equipments, they are to be rectified by the <strong>contract</strong>or at the earliest.<br />

1.0 Any break down/repair works pertaining to the air conditioners should be taken-up<br />

immediately by the <strong>contract</strong>or <strong>for</strong> effective per<strong>for</strong>mance <strong>of</strong> the air-conditioners.<br />

2.0 Per<strong>for</strong>mance test on the grills <strong>of</strong> Window/Split ACs, Water Coolers and<br />

Refrigerators shall be taken at least once in a week by the Contractor and the<br />

recorded grill temperature <strong>of</strong> the ACs should not be more than 10-11 degree<br />

Centigrade. The <strong>contract</strong>or shall record the grill temperature and all the equipments<br />