11.07.2015 Views

Technologies and Costs for Removal of Arsenic From Drinking Water

Technologies and Costs for Removal of Arsenic From Drinking Water

Technologies and Costs for Removal of Arsenic From Drinking Water

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

6. The capital costs include a redundant column to allow the system to operate while the mediais being regenerated in the other column.7. The other equipment cost elements are the brine tank, brine pump <strong>and</strong> mixer. <strong>Costs</strong> <strong>for</strong> thebrine tank were based on 30-day storage. Separate costs were prepared <strong>for</strong> the two sulfateranges based on the number <strong>of</strong> regenerations per month.8. The remaining components <strong>of</strong> the process equipment include concrete, pipe <strong>and</strong> valves <strong>and</strong>electrical <strong>and</strong> instrumentation. A cost factor <strong>of</strong> 25.02% <strong>of</strong> the manufactured equipment <strong>and</strong>activated alumina was used <strong>for</strong> these other construction cost components.9. The capital costs have been estimated from the total process costs using a factor <strong>of</strong> 2.5 <strong>for</strong>small systems <strong>and</strong> 3.33 <strong>for</strong> large systems.10. The capital costs estimated in the previous step do not include the cost <strong>of</strong> a building to housethe process equipment <strong>and</strong> other add-on costs related to the site. Housing costs were assumed<strong>for</strong> all sites. Fence <strong>and</strong> road were only assumed <strong>for</strong> those systems that have no treatment.Table 3-13 (above) shows the assumptions made <strong>for</strong> this analysis regarding the percentage <strong>of</strong>systems with no treatment in place.11. The equation <strong>for</strong> process area, which is the key variable in estimating the costs <strong>for</strong> buildings,roads, <strong>and</strong> fences has been based on the design flow <strong>of</strong> the system. The equation used <strong>for</strong>process area is:Process Area = 118.7 * Design Flow + 11812. The building cost to house the anion exchange system is $45.38/sq ft <strong>for</strong> design flows at orbelow 0.65 mgd. The following equation is used <strong>for</strong> design flows between 0.65 <strong>and</strong> 1 mgd:Building cost = 54.204 * Process Area + 148873-49

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!