concreting where ever required shall be measured separately under relevantitem of work.12.17.12.2 Security money for testing should be kept at 10 % of the value of the work.After testing of the complete sewerage system to the satisfaction of theengineer in-charge the same shall be released.12.17.13 Rate12.17.13.1 The rate shall include the cost of material <strong>and</strong> labour involved in all theoperation described above including the cost of concrete which shall bepaid separately.Urban Administration & Development Department Page 147