4.0 FUGITIVE DUST CONTROL PLAN<br />

- 5069<br />

Silo 3 Environmental Control Plan<br />

40430-PL-0005, Rev. C<br />

Jacobs-Project Number 35H19605<br />

September 23, 2003 e<br />

The section describes the method that will be used for controlling fugitive dust emissions<br />

and ensuring compliance with the required standards and site-specific limits for the Silo 3<br />

Project. Dust releases from field activities will be proactively suppressed by applying BAT<br />

dust control materials andlor implementing BAT work practices at the beginning and during<br />

field activities. RM-0047, Fugitive Dust Control Requirements, will be used as the<br />

appropriate site-specific definition <strong>of</strong> BAT for fugitive dust control together with OAC<br />

3745-17-07 and OAC 3745-17-08, to minimize the creation and dispersion <strong>of</strong> fugitive<br />

dust.<br />

4.1 SITE-SPECIFIC LIMITS<br />

The following site-specific limits will be applied:<br />

Visible particulate emission from any paved roadway or paved parking area should not<br />

exceed 1 minute during any 60-minute observation period.<br />

0 Visible particulate emissions from any unpaved roadway, unpaved parking area, project<br />

field activities, or wind erosion from storage piles should not exceed 3 minutes during<br />

any 60-minute observation period.<br />

Personnel using 40 CFR Part 60, Appendix A, Method 22 "Visual Determination <strong>of</strong> Fugitive<br />

Emission from Material Sources and Smoke Emissions for Flares," will verify compliance<br />

with these limits. Fluor Fernald will provide.Method 22 training to qualify Contractor<br />

personnel.<br />

4.2 SUPPRESSION EQUIPMENT<br />

Due to the radiological issues associated with working on the Silo 3 Project, dedicated<br />

equipment will be used for radiological work zones to avoid having to decontaminate<br />

equipment. If required by site conditions, the Contractor may, switch equipment and<br />

systems between areas after decontamination and radiological sampling verifies no and<br />

radiological scanning, switch equipment and systems between areas after decontamination<br />

and radiological scanning verifies no contamination. The proposed equipment list to<br />

suppress dust releases includes, but is not limited to, the following:<br />

0 Motor grader,<br />

Backhoe,<br />

0 Miscellaneous hand tools (shovels, brooms),<br />

Miscellaneous pumps and hoses,<br />

12