ELEMENTAL COSTING<br />

Bills of Quantities<br />

NOTE: The cost estimates presented in these norms <strong>and</strong> st<strong>and</strong>ards are a guide <strong>and</strong> are based on the<br />

calculation as at March 2008. For calculation of escalations the formula as presented in the Industry<br />

Guide published by the Department of Cooperative Governance <strong>and</strong> Traditional Affairs (COGTA) should<br />

be used.<br />

ARCHERY<br />

Should it be necessary to construct a dedicated archery fi eld measuring 120 m long x 35 m wide, the elemental cost analysis would<br />

be as follows:<br />

NO. ITEM UNITS QTY RATE R % AMOUNT R TOTALS R<br />

A. SUB-STRUCTURE, ETC.<br />

(Provisional)<br />

Removal of Trees (Size ………) No. 1 3,000.00 0.31 3,000.00<br />

Clear site m2 4674 6.00 2.87 28,044.00<br />

Removal of Topsoil incl. Carting Away m3 467 105.00 5.01 49,035.00<br />

Bulk Earthworks m3 935 35.00 3.35 32,725.00<br />

Rip & Compact In-Situ Earth to 93 % ModAASHTO m2 4674 6.00 2.87 28,044.00<br />

Herring Bone Sub-Soil Drainage m 1,145 90.00 10.54 103,050.00<br />

Storm Water Reticulation m 25 145.00 0.37 3,625.00<br />

Storm Water Catchpits, etc. No. 3 2,200.00 0.67 6,600.00<br />

Water Supply for Sprinkler System m 310 85.00 2.69 26,350.00<br />

110 mm Diameter Sleeves m 10 120.00 0.12 1,200.00<br />

Automatic Irrigation System m2 4,674 8.00 3.82 37,392.00<br />

Crusher run Base Course m3 467 230.00 10.98 107,410.00<br />

Coarse River S<strong>and</strong> Layer m2 117 7.00 0.08 819.00<br />

Compost m2 234 160.00 3.82 37,392.00<br />

Imported Topsoil (Weed Free) m3 351 130.00 4.67 45,630.00<br />

Levelling <strong>and</strong> Shaping m2 4,674 3.00 1.43 14,022.00<br />

Grass m2 4,674 15.00 7.17 70,110.00<br />

Fertiliser m2 4,674 3.00 1.43 14,022.00 608,470.00<br />

B. SPECIALIST ITEMS<br />

Targets No. 12 2,400.00 2.94 28,800.00<br />

Line demarcation m 640 4.00 0.26 2,560.00 31,360.00<br />

SUB-TOTALS 65.42 639,830.00<br />

PRELIINARIES AND GENERAL 7.85 76,780.00<br />

SUB-TOTALS 73.27 716,610.00<br />

CONTINGENCIES % 5 3.66 35,831.00<br />

PROVISION FOR ESCALATION Months 3 1.04 10,158.00<br />

SUB-TOTALS 77.97 762,599.00<br />

PROFESSIONAL FEES % 12.5 9.75 95,325.00<br />

SUB-TOTALS 87.72 857,924.00<br />

VALUE ADDED TAX % 14 12.28 120,109.00<br />

SIX LANE ARCHERY FIELD TOTAL<br />

Note: All fi gures have been rounded up.<br />

100.00 978,033.00<br />

129<br />

Elemental<br />

Costing