The cost of a golf course very specifi c to the location, topography, st<strong>and</strong>ard of play, water features, length of the course <strong>and</strong> local<br />
ground conditions.<br />
The cost of golf courses varies between R 2,000,000.00 to R 4,500,000.00 per hole, which relates to an average cost of R<br />
3,250,000.00 per hole.<br />
Similarly the cost of the other facilities that are provided such as the club house, halfway facilities vary greatly frfom location to<br />
location dependant on all of the above <strong>and</strong> all related commercial facilities that are supplied.<br />
The cost of a club house may vary from R 3,500,000.00 to a much as R 20,000,000.00<br />
GRASSED HOCKEY FIELD<br />
The elemental cost analysis indicated below is based on a centre square that provides for three cricket pitches.<br />
NO. ITEM UNITS QTY RATE R % AMOUNT R TOTALS R<br />
A. SUB-STRUCTURE, ETC. (Provisional)<br />
Removal of Trees (Size ………) No. 1 3,000.00 0.13 3,000.00<br />
Clear site m2 5941 6.00 1.54 35,646.00<br />
Removal of Topsoil incl. Carting Away m3 594 105.00 2.69 62,370.00<br />
Bulk Earthworks m3 1188 35.00 1.79 41,580.00<br />
Rip & Compact In-Situ Earth to 93 % ModAASHTO m2 5941 6.00 1.54 35,646.00<br />
Herring Bone Sub-Soil Drainage m 2,670 90.00 10.35 240,300.00<br />
Storm Water Reticulation m 30 145.00 0.19 4,350.00<br />
Storm Water Catchpits, etc. No. 5 2,200.00 0.47 11,000.00<br />
Water Supply for Sprinkler System m 420 85.00 1.54 35,700.00<br />
110 mm Diameter Sleeves m 10 120.00 0.05 1,200.00<br />
Automatic Irrigation System m2 5,941 8.00 2.05 47,528.00<br />
Crusher run Base Course m3 594 230.00 5.89 136,620.00<br />
Coarse River S<strong>and</strong> Layer m2 149 7.00 0.04 1,043.00<br />
Compost m3 297 160.00 2.05 47,528.00<br />
Imported Topsoil (Weed Free) m3 446 130.00 2.50 57,980.00<br />
Levelling <strong>and</strong> Shaping m2 5,941 3.00 0.77 17,823.00<br />
Grass m2 5,941 15.00 3.84 89,115.00<br />
Fertiliser m2 5,941 3.00 0.77 17,823.00 886,252.00<br />
B. SPECIALIST ITEMS<br />
Goal Posts (Including Net) No. 2 15,000.00 1.29 30,000.00<br />
Demarcation Lines m 495 12.00 0.26 5,940.00<br />
Scoreboard No. 1 15,000.00 0.65 15,000.00 50,940.00<br />
SUB-TOTALS 40.37 937,192.00<br />
PRELIMINARIES AND GENERAL 8.03 112,463.00<br />
SUB-TOTALS 48.40 1,049,655.00<br />
CONTINGENCIES % 5 3.75 52,483.00<br />
PROVISION FOR ESCALATION Months 3 1.06 14,879.00<br />
SUB-TOTALS 53.21 1,117,017.00<br />
PROFESSIONAL FEES % 10 7.97 111,702.00<br />
SUB-TOTALS 61.18 1,228,719.00<br />
VALUE ADDED TAX % 14 12.28 172,021.00<br />
GRASSED HOCKEY FIELD TOTAL<br />
Note: All fi gures have been rounded up.<br />
73.46 1,400,740.00<br />