1.4.14 Netball<br />

Netball is a team game based on running, jumping, throwing <strong>and</strong> catching. Teams may include up to 12<br />

players but only 7 may take to the court at any one time.<br />

The aim of the game is to score as many goals as possible by throwing a ball through a hoop situated<br />

on top of a post. The game is played on a hard court.<br />

The court<br />

The court is 30.5 metres long <strong>and</strong> 15.25 metres wide <strong>and</strong> is divided into thirds. There is a centre circle<br />

with a diameter of 900 mm <strong>and</strong> two goal circles which are semi-circles measuring 4.9 metres in radius.<br />

All lines are part of the court <strong>and</strong> measure 50 mm in width.<br />

The goal posts are placed mid-point on each goal line <strong>and</strong> measure 3.05 metre in height. The goal<br />

rings have an internal diameter of 380 mm. The goal rings project horizontally from the post on a single<br />

attachment measuring 150 mm.<br />

The ball<br />

The ball is made of leather, rubber or similar material, weighing 400 – 450 grams <strong>and</strong> has a circumference<br />

of 690 – 710 mm.<br />

Construction of court<br />

The courts have a hard surface <strong>and</strong> may have an ashphalt or an artifi cial synthetic surface. The substrate<br />

preparation is the same for both types of surfaces.<br />

Artifi cial synthetic surfaces on concrete substrates<br />

The surface preparation for artifi cial playing surfaces may be briefl y described as follows:<br />

• The sub-surface earth needs to be levelled <strong>and</strong> compacted to 95 % Modifi ed ASSHTO with<br />

a maximum cross slope of 1%.<br />

• Sub-Surface drainage system to be installed below all fi eld surfaces (in terms with Civil<br />

Engineering design). Install sub-surface drainage comprising 110 mm diameter agricultural<br />

drains placed in 450 x 600 mm deep herring bone drainage system at 6 metre intervals <strong>and</strong><br />

to entire perimeter of the cricket fi eld.<br />

• Sub-surface drains to be lined with a “Bidum” Hessian layer <strong>and</strong> fi lled in with 19 mm<br />

crusher run stone.<br />

• Sub-Surface drains to connect at the lowest point to a storm water catch pit which should<br />

be connected to a storm water main.<br />

• The sub-surface drains are then covered with a 100 mm thick layer of crusher run to assist<br />

in the sub-surface drainage.<br />

57<br />

Netball