RUGBY FIELD<br />
The elemental cost analysis indicated below is based on a football fi eld with a size of 144 m x 70 m.<br />
NO. ITEM UNITS QTY RATE R % AMOUNT R TOTALS R<br />
A. SUB-STRUCTURE, ETC. (Provisional)<br />
Removal of Trees (Size ………) No. 1 3,000.00 0.13 3,000.00<br />
Clear site m2 11400 6.00 3.05 68,400.00<br />
Removal of Topsoil incl. Carting Away m3 1140 105.00 5.34 119,700.00<br />
Bulk Earthworks m3 2280 35.00 3.56 79,800.00<br />
Rip & Compact In-Situ Earth to 93 % ModAASHTO m2 11400 6.00 3.05 68,400.00<br />
Herring Bone Sub-Soil Drainage m 2,520 90.00 10.11 226,800.00<br />
Storm Water Reticulation m 30 145.00 0.19 4,350.00<br />
Storm Water Catchpits, etc. No. 5 2,200.00 0.49 11,000.00<br />
Water Supply for Sprinkler System m 428 85.00 1.62 36,380.00<br />
110 mm Diameter Sleeves m 10 120.00 0.05 1,200.00<br />
Automatic Irrigation System m2 11,400 8.00 4.07 91,200.00<br />
Crusher run Base Course m3 1140 230.00 11.69 262,200.00<br />
Coarse River S<strong>and</strong> Layer m2 285 7.00 0.09 1,995.00<br />
Compost m3 570 160.00 4.07 91,200.00<br />
Imported Topsoil (Weed Free) m3 855 130.00 4.96 111,150.00<br />
Levelling <strong>and</strong> Shaping m2 11,400 3.00 1.53 34,200.00<br />
Grass m2 11,400 15.00 7.63 171,000.00<br />
Fertiliser m2 11,400 3.00 1.53 34,200.00 1,416,175.00<br />
B. SPECIALIST ITEMS<br />
Goal Posts No. 2 15,000.00 1.34 30,000.00<br />
Padding to Goal Posts No. 4 4,500.00 0.80 18,000.00<br />
Demarcation Lines m 1,206 12.00 0.65 14,472.00<br />
Scoreboard No. 1 15,000.00 0.67 15,000.00 77,472.00<br />
SUB-TOTALS 66.61 1,493,647.00<br />
PRELIINARIES AND GENERAL 7.99 179,238.00<br />
SUB-TOTALS 74.60 1,672,885.00<br />
CONTINGENCIES % 5 3.73 83,644.00<br />
PROVISION FOR ESCALATION Months 4 1.41 31,618.00<br />
SUB-TOTALS 79.74 1,788,147.00<br />
PROFESSIONAL FEES % 10 7.98 178,815.00<br />
SUB-TOTALS 87.72 1,966,962.00<br />
VALUE ADDED TAX % 14 12.28 275,375.00<br />
RUGBY FIELD TOTAL 100.00 2,242,337.00<br />
Note: All fi gures have been rounded up.<br />