Painting<br />
ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT<br />
1<br />
BILL NO. 16<br />
PROVISIONAL SUMS<br />
Unless otherwise described the Preambles <strong>and</strong> full descriptions of the items in the previouse sections will apply equally to this section.<br />
NOTE: The following Prime Cost Amounts are NET <strong>and</strong> do not include any Builder’s Discount. ………………………………………<br />
Sundry Steelwork, Gates, Screens, etc.<br />
Allow the sum of R 75,000.00 for the sundry steelwork<br />
Installation complete. Item 75,000.00<br />
2 Allow for profi t upon above if required. Item 1,875.00<br />
3 Attend upon the sundry steelwork installation fi rm.<br />
Aluminium Windows<br />
Item 1,875.00<br />
4 Allow the sum of R 265,000.00 for the aluminium windows installed Item<br />
complete.<br />
265,000.00<br />
5 Allow for profi t upon above if required. Item 6,625.00<br />
6 Attend upon the aluminium window installation fi rm.<br />
Paraplegic Fittings<br />
Item 6,625.00<br />
7 Allow the sum of R 15,000.00 for the paraplegic fi ttings<br />
installed complete. Item 15,000.00<br />
8 Allow for profi t upon above if required. Item 375.00<br />
9 Attend upon the paraplegic fi ttings installation fi rm.<br />
Change Room Fittings, Built-In-Cupboards, etc.<br />
Item 375.00<br />
10 Allow the sum of R 50,000.00 for the built-in-cupboard installation Item<br />
complete.<br />
50,000.00<br />
11 Allow for profi t upon above if required. Item 1,250.00<br />
12 Attend upon the built-in-cupboard installation fi rm.<br />
Roller Shutter Doors<br />
Item 1,250.00<br />
13 Allow the sum of R 18,000.00 for the roller shutter door installation Item<br />
complete.<br />
18,000.00<br />
14 Allow for profi t upon above if required. Item 450.00<br />
15 Attend upon the roller shutter door installation fi rm. Item 450.00<br />
SUB-TOTAL TO COLLECTION R<strong>and</strong> 444,150.00<br />
163<br />
Painting