NETBALL COURT<br />
The fi gures indicated below allow for an external hard court 30.50 m long x 15.25 m wide.<br />
NO. ITEM UNITS QTY RATE R % AMOUNT R TOTALS R<br />
A. SUB-STRUCTURE, ETC. (Provisional)<br />
Removal of Trees (Size ………) No. 1 3,000.00 1.17 3,000.00<br />
Clear site m2 611 6.00 1.43 3,666.00<br />
Removal of Topsoil incl. Carting Away m3 61 105.00 2.49 6,405.00<br />
Bulk Earthworks m3 122 35.00 1.66 4,270.00<br />
Rip & Compact In-Situ Earth to 93 % ModAASHTO m2 611 6.00 1.43 3,666.00<br />
Sub-Soil Drainage to Perimeter m 88 90.00 3.08 7,920.00<br />
Storm Water Reticulation m 25 145.00 1.41 3,625.00<br />
Storm Water Catchpits, etc. No. 2 2,200.00 1.71 4,400.00<br />
Crusher run Base Course m3 61 230.00 5.46 14,030.00<br />
Coarse River S<strong>and</strong> Layer m2 15 7.00 0.04 105.00<br />
Concrete in Surface Beds m2 285 145.00 16.09 41,325.00<br />
Asphalt to Final Finish m2 285 70.00 7.77 19,950.00<br />
Polyurethane Coating to Asphalt m2 285 165.00 18.30 47,025.00<br />
Line Markings m 153 12.00 0.71 1,836.00 161,223.00<br />
B. SPECIALIST ITEMS<br />
Posts No. 2 3,800.00 2.96 7,600.00 7,600.00<br />
SUB-TOTALS 65.71 168,823.00<br />
PRELIINARIES AND GENERAL 7.89 20,259.00<br />
SUB-TOTALS 73.60 189,082.00<br />
CONTINGENCIES % 5 3.68 9,454.00<br />
PROVISION FOR ESCALATION Months 2 0.70 1,787.00<br />
SUB-TOTALS 77.97 200,323.00<br />
PROFESSIONAL FEES % 12.5 9.75 25,040.00<br />
SUB-TOTALS 87.72 225,363.00<br />
VALUE ADDED TAX % 14 12.28 31,551.00<br />
NETBALL HARD COURT TOTAL 100.00 256,914.00<br />
Note: All fi gures have been rounded up.<br />
139<br />
Elemental<br />
Costing