Construction of a lawn korfball fi eld<br />

The construction of the korfball fi eld should be done with great care <strong>and</strong> all materials used should be<br />

chemically <strong>and</strong> physically analysed to ensure that the fi nal product produces a korfball fi eld that will<br />

prevent the fi eld from disintegrating when used.<br />

• Remove all top soil from the area of the square.<br />

• Excavate out natural earth to a depth of at least 450 mm to Civil Engineering specifi cation.<br />

(Depth may vary dependant on the carrying capacity of the soil)<br />

• Rip <strong>and</strong> compact in-situ earth to 95% modifi ed AASHTO.<br />

• Install sub-surface drainage comprising 110 mm diameter agricultural drains placed in 450<br />

x 600 mm deep herring bone drainage system at 6 metre intervals <strong>and</strong> to entire perimeter<br />

of the cricket pitch or square.<br />

• Sub-surface drains to be lined with a “Bidum” Hessian layer <strong>and</strong> fi lled in with 19 mm<br />

crusher run stone.<br />

• Sub-Surface drains to connect at the lowest point to a storm water catch pit which should<br />

be connected to a storm water main.<br />

• The sub-surface drains are then covered with a 150 mm thick layer of crusher run to assist<br />

in the sub-surface drainage compacted to 95 % modifi ed AASHTO.<br />

• Lay strip of 250 micron plastic down the edges of the excavation to prevent encroachment<br />

of invader grass species.<br />

• The crusher run layer is covered with a 50 mm thick layer of course river s<strong>and</strong>.<br />

• Add 100 mm thick layer of loam soil <strong>and</strong> mix in fertiliser as required by soil analysis.<br />

• Roll in 150 mm thick clay in layers (Dependant on the results of the chemical analysis,<br />

fertiliser to promote root growth should be mixed into the clay ) <strong>and</strong> compact.<br />

• Wash grass sods to remove all soil <strong>and</strong> tease sprigs apart. Lay sprigs on bulli (clay) surface<br />

<strong>and</strong> add a thin layer of sieved bulli to a depth of not more than 15 mm(sieve aperture of<br />

maximum 10 mm) over the grass <strong>and</strong> smooth.<br />

• Apply fertiliser <strong>and</strong> water twice daily with a fi ne nozzle spray until grass shown signs of<br />

sprouting.<br />

• Continue to water until the grass has covered the pitch.<br />

• Once the grass has established, cut to 15 mm <strong>and</strong> rub in sieved (1.25 mm gauge screen)<br />

bulli, to a smooth even surface, making sure that the grass tips protrude above the bulli.<br />

• Water daily, as required, until the grass shoots push through.<br />

Korfball<br />