Concrete Formwork & Reinforcement<br />

149<br />

Concrete Formwork<br />

& Reinforcement<br />

ITEM DESCRIPTION UNIT QUANTITY RATE AMOUNT<br />

15 Ditto to falls. m2 80 15.00 1,200.00<br />

16 Strike off <strong>and</strong> cure top surface of concrete <strong>and</strong> power fl oat to a smooth<br />

uniform level.<br />

FORMWORK, ETC. TO CONCRETE<br />

General formwork (use <strong>and</strong> waste) to:<br />

m2 621 16.00 9,936.00<br />

15 Soffi ts of slabs m2 603 90.00 54,270.00<br />

16 Sides <strong>and</strong> soffi ts of beams. m2 576 90.00 51,840.00<br />

17 Sides of inverted beams. m2 59 90.00 5,310.00<br />

18 Sides of square or rectangular columns. m2 224 94.00 21,056.00<br />

19 Raking soffi t of stairs m2 26 120.00 3,120.00<br />

20 Edge not exceeding 150 mm high. m 85 23.80 2,023.00<br />

21 Risers exceeding 150 mm <strong>and</strong> not exceeding 300 mm high. m 83 27.20 2,257.60<br />

22 Raking sp<strong>and</strong>ril edge of stairs<br />

SLEEVES, SLIP JOINTS etc.<br />

m 29 27.20 788.80<br />

23 50 mm Diameter sleeves through 220 mm thick reinforced concrete<br />

beam.<br />

No. 8 4.25 34.00<br />

24 110 mm Diameter sleeves through 175 mm thick reinforced concrete<br />

slab.<br />

No. 4 6.80 27.20<br />

25 Slip joint comprising two layers of 3 mm tempered hardwood with<br />

well greased abutting surfaces between concrete <strong>and</strong> brick bearing<br />

surfaces not exceeding 230 mm wide.<br />

m 120 18.70 2,244.00<br />

EXPANSION JOINTS<br />

Expansion joints with polysulphide sealant fi lled into joints in concrete surfaces : (Provisional)<br />

26 3 mm Wide x 40 mm deep saw cut joint.<br />

HOISTING INTO POSITION AND FIXING OF STEEL<br />

REINFORCING (Provisional)<br />

m 212 20.40 4,324.80<br />

27 Mild tensile steel reinfrocing bars in various lengths. t 2 8,450.00 16,900.00<br />

28 High tensile ditto.<br />

HOISTING INTO POSITION AND FIXING STEEL MESH<br />

REINFORCING (Provisional)<br />

t 28 8,450.00 236,600.00<br />

29 Mesh Ref. 193 m2 995 27.00 26,865.00<br />

30 Mesh Ref. 345 m2 5 43.00 215.00<br />

SUB-TOTAL TO COLLECTION R<strong>and</strong> 439,011.40<br />

ITEM DESCRIPTION<br />

CONCRETE FORMWORK & REINFORCEMENT<br />

COLLECTION<br />

UNIT QUANTITY RATE AMOUNT<br />

Total from Page Number 8 309,241.00<br />

Total from Page Number 9 439,011.40<br />

TOTAL TO SUMMARY R<strong>and</strong> 748,252.40