ATHLETICS TRACK ( 8 LANES)<br />
Elemental<br />
Costing<br />
An eight lane athletics track with a synthetic running surface <strong>and</strong> all track <strong>and</strong> fi eld events would cover an area of 16774 m2<br />
NO. ITEM UNITS QTY RATE R % AMOUNT R TOTALS R<br />
A. SUB-STRUCTURE, ETC.<br />
(Provisional)<br />
Removal of Trees (Size ………) No. 1 3,000.00 0.04 3,000.00<br />
Clear site m2 16774 6.00 1.43 100,644.00<br />
Removal of Topsoil incl. Carting Away m3 1677 105.00 2.50 176,085.00<br />
Bulk Earthworks m3 3355 35.00 1.67 117,425.00<br />
Rip & Compact In-Situ Earth to 93 % ModAASHTO m2 16774 6.00 1.43 100,644.00<br />
Herring Bone Sub-Soil Drainage m 3,000 90.00 3.83 270,000.00<br />
Storm Water Reticulation m 50 145.00 0.10 7,250.00<br />
Storm Water Catchpits, etc. No. 5 2,200.00 0.16 11,000.00<br />
Water Supply for Sprinkler System m 269 85.00 0.32 22,865.00<br />
110 mm Diameter Sleeves m 177 120.00 0.30 21,240.00<br />
Automatic Irrigation System m2 10,974 8.00 1.25 87,792.00<br />
Crusher run Base Course m3 1677 230.00 5.47 385,710.00<br />
Coarse River S<strong>and</strong> Layer m2 10,974 7.00 1.09 76,818.00<br />
Compost m2 46 160.00 0.10 7,360.00<br />
Imported Topsoil (Weed Free) m3 1097 130.00 2.02 142,610.00<br />
Levelling <strong>and</strong> Shaping m2 16,774 3.00 0.71 50,322.00<br />
Grass m2 10,974 15.00 2.34 164,610.00<br />
Fertiliser m2 10,974 3.00 0.47 32,922.00 1,778,297.00<br />
B. SPECIALIST ITEMS<br />
13 mm Synthetic Surface to Running Track m2 5,550 366.00 28.82 2,031,300.00<br />
20 mm Polyurethane High Impact Surface m2 235 562.00 1.87 132,070.00<br />
25 mm S<strong>and</strong>wich Polyurethane to Water Jump m2 15 703.00 0.15 10,545.00<br />
Aluminium Kerbing m 400 320.00 1.82 128,000.00<br />
Colour Coded Indicator Plates No. 164 100.00 0.23 16,400.00<br />
Paint Markings Item 1 104,000.00 1.48 104,000.00<br />
S<strong>and</strong> Pit to Long & Triple Jump No. 2 84,000.00 2.38 168,000.00<br />
Take Off Board to Long & Triple Jump No. 8 9,400.00 1.07 75,200.00<br />
Shot Put Ring & Boards No. 2 6,800.00 0.19 13,600.00<br />
Discus & Hammer Throw Ring No. 2 4,800.00 0.14 9,600.00<br />
Hammer Throw Protective Neting Item 1 76,000.00 1.08 76,000.00<br />
Cast-in Stainless Steel Sockets for Above Set 2 8,000.00 0.23 16,000.00<br />
Adjustable Water Jump Steeplechase Hurdle No. 1 9,600.00 0.14 9,600.00 2,790,315.00<br />
SUB-TOTALS 64.83 4,568,612.00<br />
PRELIINARIES AND GENERAL 7.78 548,233.00<br />
SUB-TOTALS 72.61 5,116,845.00<br />
CONTINGENCIES % 5 3.63 255,842.00<br />
PROVISION FOR CURRENCY EXCHANGE RATES# 0.71 50,000.00<br />
PROVISION FOR ESCALATION Months 4 1.37 96,708.00<br />
SUB-TOTALS 78.32 5,519,395.00<br />
PROFESSIONAL FEES % 12 9.40 662,327.00<br />
SUB-TOTALS 87.72 6,181,722.00<br />
VALUE ADDED TAX % 14 12.28 865,441.00<br />
EIGHT LANE ATHLETICS TRACK TOTAL<br />
Note: All fi gures have been rounded up.<br />
100.00 7,047,163.00<br />