07.04.2013 Views

part 1: overview of cogeneration and its status in asia - Fire

part 1: overview of cogeneration and its status in asia - Fire

part 1: overview of cogeneration and its status in asia - Fire

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Examples <strong>of</strong> <strong>cogeneration</strong> projects implemented <strong>in</strong> Asia 75<br />

2.4.2 Economic evaluation <strong>of</strong> <strong>cogeneration</strong> options<br />

Four different options were considered for compar<strong>in</strong>g with the present case, as follows:<br />

1. Use <strong>of</strong> low pressure boilers for process steam only , <strong>and</strong> no power generation on site;<br />

2. Use <strong>of</strong> a high pressure boiler <strong>and</strong> a back pressure turb<strong>in</strong>e to meet 30-40 per cent <strong>of</strong> the<br />

power dem<strong>and</strong>;<br />

3. Use <strong>of</strong> a high pressure boiler <strong>of</strong> a higher capacity, a back pressure turb<strong>in</strong>e <strong>and</strong> an<br />

additional condens<strong>in</strong>g turb<strong>in</strong>e, or a s<strong>in</strong>gle extraction-condens<strong>in</strong>g turb<strong>in</strong>e to meet 60-70 per<br />

cent <strong>of</strong> the power dem<strong>and</strong>;<br />

4. The same as (2), but all the power needs <strong>of</strong> the factory are met <strong>in</strong> this option.<br />

2.4.3 No power generation<br />

To meet the <strong>in</strong>creased steam dem<strong>and</strong> <strong>of</strong> digesters <strong>and</strong> for avail<strong>in</strong>g st<strong>and</strong>-by capacity, it was<br />

proposed <strong>in</strong> this case to replace an old boiler by a new fluidized bed combustion boiler hav<strong>in</strong>g<br />

a capacity to produce 10 tons <strong>of</strong> dry saturated steam per hour at 10.5 bar. Entire power<br />

requirement was to be met by the purchase <strong>of</strong> power from the utility grid, the diesel generator<br />

cont<strong>in</strong>u<strong>in</strong>g to provide the back up <strong>in</strong> case <strong>of</strong> power outages.<br />

2.4.4 30-40 per cent power generation<br />

The erratic power supply <strong>of</strong> the utility makes it absolutely necessary to have at least a<br />

capacity to self-generate 30-40 per cent <strong>of</strong> the power need (600-700 kW) to avoid production<br />

losses. Though a diesel generator is available, the power generated from this unit is quite<br />

expensive <strong>and</strong> the ma<strong>in</strong>tenance cost <strong>of</strong> this unit is expected to mount with time.<br />

As there was a need to acquire a new boiler, this option considered the option <strong>of</strong> generat<strong>in</strong>g<br />

steam at 42 bar <strong>and</strong> 440°C. The steam could be supplied to a back pressure turb<strong>in</strong>e to<br />

generate around 30-40 per cent <strong>of</strong> the power dem<strong>and</strong> <strong>of</strong> the factory, <strong>and</strong> the steam leav<strong>in</strong>g<br />

the turb<strong>in</strong>e at a pressure <strong>of</strong> 4 Bar can be sent to fulfil process heat<strong>in</strong>g needs.<br />

The <strong>in</strong>itial <strong>in</strong>vestment as well as the operat<strong>in</strong>g cost <strong>of</strong> this system was found to be lower than<br />

a diesel eng<strong>in</strong>e. The fuel used <strong>in</strong> the boiler is cheap <strong>and</strong> available <strong>in</strong> abundance. Moreover,<br />

only the <strong>in</strong>cremental cost <strong>of</strong> fuel required generat<strong>in</strong>g the same quantity <strong>of</strong> steam at higher<br />

pressure <strong>and</strong> temperature was considered, which is only 20 per cent higher. The cost <strong>of</strong><br />

power generation worked out to be 36 per cent lower than that with the diesel generator.<br />

From the practical side, a smaller size would mean the use <strong>of</strong> <strong>in</strong>efficient s<strong>in</strong>gle stage turb<strong>in</strong>e<br />

<strong>and</strong> low voltage generator. This may lead to large imbalance <strong>in</strong> the system due to variations <strong>in</strong><br />

the process steam <strong>and</strong> power dem<strong>and</strong>s. The system balance can be achieved only by<br />

operat<strong>in</strong>g the system at low plant load factor, thereby compromis<strong>in</strong>g the overall efficiency <strong>and</strong><br />

productivity <strong>of</strong> the factory.<br />

2.4.5 60-70 per cent <strong>of</strong> power generation<br />

At this level <strong>of</strong> power generation, higher productivity can be guaranteed with practically no<br />

production losses. Installation <strong>of</strong> a higher capacity (14 tons/hour) <strong>and</strong> higher pressure (42 bar<br />

<strong>and</strong> 445°C) boiler was considered. As much as 6-7 tons/hour <strong>of</strong> steam could be used <strong>in</strong> the<br />

back pressure turb<strong>in</strong>e <strong>and</strong> match the process steam dem<strong>and</strong>. The rema<strong>in</strong><strong>in</strong>g high-pressure<br />

steam can be sent to a condens<strong>in</strong>g turb<strong>in</strong>e for additional power generation. The latter will also<br />

assure to absorb the fluctuations <strong>in</strong> the process steam dem<strong>and</strong>, without affect<strong>in</strong>g the power<br />

output adversely. Further, the use <strong>of</strong> a s<strong>in</strong>gle multistage backpressure cum condens<strong>in</strong>g<br />

turb<strong>in</strong>e will assure <strong>in</strong>creased power output <strong>and</strong> higher system efficiency.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!