10. PROJECT SUMMARIES<br />

The following pages provide a concise project summary for each SEP project. The section,<br />

organized by SEP ID Number, includes the following summary information, and additional<br />

information for each project can be found in the Appendices.<br />

• Basic information including the project SEP ID Number, name, and project location.<br />

• Project prioritization, as committed to by the campus upon review of the preliminary<br />

project list. Tier 1 projects formed a committed energy savings level to the Investor<br />

Owned Utilities. Tier 2 projects reflect the campus’ planned projects to achieve<br />

approximately 150% of the committed energy savings. Backup projects serve as<br />

potential projects the campus may consider or substitute for other projects at any time.<br />

It should be noted that energy savings for select projects may have been refined since<br />

the preliminary project list, as discussed in Section 2 of this report. (Note that all <strong>UC</strong>LA<br />

projects will be shown as “Backup” because the campus did not formally commit to<br />

projects in conjunction with the IOU deadlines.)<br />

• The Calculation File Name provides a reference for the file name, and path if applicable,<br />

of the energy calculation which is included as a soft copy in the appendix of this report.<br />

• The Project Description Reference provides the titles of the projects (Air Handler Project<br />

1, Lighting Project 3, etc) as defined in the <strong>Energy</strong> Efficiency Project Description section<br />

earlier in this report.<br />

• Building <strong>Energy</strong> Savings. The project energy savings are summarized at the building<br />

level, which include chilled water and heating hot water or steam, if supplied from a<br />

central plant, as well as the direct gas or electric savings. The total cost savings are<br />

estimated based on the purchased utility savings (including central plant and<br />

cogeneration impacts) and campus recharge rates.<br />

• Incentive Calculation Basis. The projected utility incentive is provided using the<br />

equivalent electric and gas savings, which convert chilled water and heating hot water or<br />

steam savings to electric or gas savings using the central plant efficiencies. The<br />

incentive shown in this section is the gross potential incentive, without consideration of a<br />

project cost cap.<br />

• Project Cost Summary. Details are displayed for the cost buildup, including appropriate<br />

multipliers and soft costs. If the source of a cost is the construction cost, contingency,<br />

engineering, construction management and project management is added. If the bare<br />

costs are known, the applicable city multipliers, tax, and O&P included obtaining the<br />

estimated construction cost, to which the soft costs are added.<br />

• Project Economics Summary. The project costs, savings and resulting simple payback<br />

are calculated. The utility incentive stated here takes into consideration the project cost<br />

cap, and is highlighted if it is capped by the project cost. The monetary savings is based<br />

on the purchased utility savings and campus recharge rate.<br />

2413.01/Reports/<strong>UC</strong> SEP Final Report – <strong>UC</strong>LA.doc 10-1 December 31, 2008<br />