<strong>Strategic</strong> <strong>Energy</strong> <strong>Plan</strong> Projects<br />

SEP ID<br />

Number Project Name<br />

D1005 CV Rebalance<br />

D3022 Monitoring Based Commissioning<br />

GONDA CENTER<br />

<strong>Campus</strong>: LOS ANGELES<br />

Location:<br />

Building Key: 04C4315<br />

Funding Source: STATE<br />

Year Built:<br />

Electric<br />

(kWh/yr)<br />

Peak<br />

Demand<br />

(kW)<br />

LOS ANGELES<br />

1998<br />

Building Savings Cost<br />

HW/Steam<br />

(MMBTU/yr)<br />

Gas<br />

(th/yr)<br />

Chilled<br />

Water<br />

(ton-hr/yr)<br />

Purchased<br />

Utility Cost<br />

Savings<br />

($/yr)<br />

211,550 24.0 1,194 0 59,189 $28,923<br />

236,632 27.0 0 25,416 0 $34,780<br />

Basic Gross Area (sf): 125,202<br />

Building Type: COMPLEX<br />

Primary Asset Type: Office Support<br />

Secondary Asset Type: Office<br />

Project<br />

Cost<br />

($)<br />

Gross<br />

Potential<br />

Incentive<br />

($)<br />

Net<br />

Cost ($)<br />

Committed Tier:<br />

Simple<br />

Payback<br />

(yr)<br />

Backup<br />

$86,096 $77,061 $17,219 0.6<br />

Committed Tier:<br />

Backup<br />

$211,707 $82,208 $129,499 3.7<br />

Totals 448,182 51.0 1,194 25,416 59,189 $63,703 $297,804 $159,269 $146,718 2.3<br />

Building<br />

Benchmarking<br />

Baseline<br />

Implement Partnership Projects<br />

Implement SEP Projects<br />

Equivalent<br />

Electricity<br />

(kWh/yr)<br />

Equivalent<br />

Natural Gas<br />

(th/yr)<br />

Equivalent Electric<br />

<strong>Energy</strong> Use Index<br />

(kWh/sf-yr)<br />

Equivalent Natural<br />

Gas <strong>Energy</strong> Use<br />

Index (th/sf-yr)<br />

Source <strong>Energy</strong><br />

Use Index<br />

(kBTU/sf-yr)<br />

3,169,500 148,300 25.3 1.2<br />

377.6<br />

3,169,500 148,300 25.3 1.2<br />

377.6<br />

2,673,967 107,959 21.4 0.9<br />

304.9<br />

Assumed Incentives: Central <strong>Plan</strong>t Efficiencies:<br />

Electricity $0.24 per annual kWh<br />

th/MMBTU: 12.5<br />

Natural Gas $1 per annual therm<br />

kWh/ton-hr: 0.8<br />

Cap 80% project cost<br />

th/ton-hr: 0.0<br />

Percent<br />

Savings<br />

(%)<br />

N/A<br />

0.0%<br />

19.3%<br />

Source <strong>Energy</strong> Use Conversion Factors:<br />

10.239 kBTU per kWh 100 kBTU per th