PROJECT DETAIL REPORT<br />

SEP Project ID Number:<br />

Project: S-1 to 11 except 9 - CAV to VAV<br />

<strong>Campus</strong>: LOS ANGELES<br />

Location: LOS ANGELES<br />

Building: BOELTER HALL<br />

Building Key: 04C4343<br />

Basic Gross Area (sf): 373,904<br />

Calculation File:<br />

Project <strong>Energy</strong> Savings Summary<br />

Electric (kWh/yr):<br />

Peak Demand (kW):<br />

Gas (th/yr):<br />

Chilled Water (ton-hr/yr):<br />

HW/Steam (MMBTu/yr):<br />

Project Cost Summary<br />

D1052<br />

Building <strong>Energy</strong> Savings Incentive Calculation Basis<br />

557,218<br />

15.0<br />

0<br />

320,081<br />

10,256<br />

Equipment Description Qty<br />

\36. Boelter Hall\1. <strong>UC</strong>LA MZ_DD_VAV Boelter Hall S-1 to 11 except 9 - CAV to VAV.xls<br />

Project Description Reference(s): Air Handler Project 2. Convert Constant Volume Air Handlers to Variable Air Volume.<br />

Assumed Incentive Rates: Central <strong>Plan</strong>t Efficiencies:<br />

Electricity $0.24 per annual kWh th/MMBTU: 12.5<br />

Natural Gas $1 per annual therm kWh/ton-hr: 0.8<br />

th/ton-hr: 0.0<br />

Equivalent Electric Savings (kWh/yr):<br />

Equivalent Gas Savings (th/yr):<br />

Anticipated Gross Incentive:<br />

Bare Material Extended Bare<br />

Cost per Unit ($) Material Cost ($)<br />

<strong>Campus</strong> Prioritization and Schedule<br />

Project Tier:<br />

Start Preliminary Engineering:<br />

Scheduled Completion:<br />

Bare Labor Cost<br />

per Unit ($)<br />

Extended Bare<br />

Labor Cost ($)<br />

813,283<br />

128,200<br />

$323,388<br />

Backup<br />

Note: Where the anticipated gross incentive exceeds 80% of the total project<br />

cost, the incentive is capped. The net incentive amount is shown below in the<br />

Project Cost Summary.<br />

Dart Control 10 $8,710.00 $89,278 $2,900.00 $32,509<br />

3 hp VFD 3 $1,525.00 $4,689 $455.00 $1,530<br />

Dart @ zone 95 $440.00 $42,845 $128.00 $13,631<br />

5 hp VFD 2 $1,675.00 $3,434 $455.00 $1,020<br />

2 hp VFD 2 $700.00 $1,435 $400.00<br />

$897<br />

10 hp VFD 5 $1,975.00 $10,122 $545.00 $3,055<br />

15 hp VFD 4 $2,275.00 $9,328 $820.00 $3,677<br />

City: <strong>Los</strong> <strong>Angeles</strong><br />

City Index Material Multiplier:<br />

City Index Labor Multiplier:<br />

102.5%<br />

112.1%<br />

Raw Costs:<br />

Sales Tax: 8.25%<br />

Contractor O&P: 12.00%<br />

Subtotals:<br />

Contingency:<br />

Engineering:<br />

Construction Phase:<br />

Project Management:<br />

10.00%<br />

15.00%<br />

5.00%<br />

6.00%<br />

$161,130 $56,319<br />

$13,293<br />

$20,931<br />

$195,354<br />

$19,535<br />

$42,641<br />

$14,214<br />

$17,056<br />

N/A<br />

$6,758<br />

$63,077<br />

$6,308<br />

Totals: $214,889 $69,385<br />

Total Project Cost: $358,186<br />

Project Economic Summary, Including Cogeneration and Purchased Utility Impacts<br />

Total Project Cost: $358,186<br />

Rebate/Incentive*:<br />

$286,549<br />

Net Project Cost: $71,637<br />

Net Simple Payback Period (yrs): 0.6<br />

Total Purchased Electricity Savings (kWh/yr):<br />

Total Purchased Gas Savings (th/yr):<br />

Total Purchased Annual Cost Savings ($/yr):<br />

1,427,651<br />

0<br />

$125,633<br />

*Highlighted incentives have been capped at 80% of the total project cost. It is recommended that these projects be bundled together with other projects to maximize<br />

incentive funding.