PROJECT DETAIL REPORT<br />

SEP Project ID Number:<br />

Project: SAC Pool: Variable Speed Circulation Pumps<br />

<strong>Campus</strong>: LOS ANGELES<br />

Location: LOS ANGELES<br />

Building: CAMPUSWIDE<br />

Building Key: 04CWIDE<br />

Basic Gross Area (sf):<br />

Calculation File:<br />

Project <strong>Energy</strong> Savings Summary<br />

Electric (kWh/yr):<br />

Peak Demand (kW):<br />

Gas (th/yr):<br />

Chilled Water (ton-hr/yr):<br />

HW/Steam (MMBTu/yr):<br />

Project Cost Summary<br />

D3211<br />

<strong>UC</strong>LA Pools 051208 AML.xls<br />

Project Description Reference(s): Pool Project 1. Variable Speed Drives and High Efficiency Motors for Filter Pumps.<br />

Building <strong>Energy</strong> Savings Incentive Calculation Basis<br />

36,809<br />

Equipment Description Qty<br />

0.0<br />

0<br />

0<br />

0<br />

Assumed Incentive Rates: Central <strong>Plan</strong>t Efficiencies:<br />

Electricity $0.24 per annual kWh th/MMBTU: 12.5<br />

Natural Gas $1 per annual therm kWh/ton-hr: 0.8<br />

th/ton-hr: 0.0<br />

Equivalent Electric Savings (kWh/yr):<br />

Equivalent Gas Savings (th/yr):<br />

Anticipated Gross Incentive:<br />

Bare Material Extended Bare<br />

Cost per Unit ($) Material Cost ($)<br />

<strong>Campus</strong> Prioritization and Schedule<br />

Project Tier:<br />

Start Preliminary Engineering:<br />

Scheduled Completion:<br />

Bare Labor Cost<br />

per Unit ($)<br />

36,809<br />

0<br />

$8,834<br />

Note: Where the anticipated gross incentive exceeds 80% of the total project<br />

cost, the incentive is capped. The net incentive amount is shown below in the<br />

Project Cost Summary.<br />

Extended Bare<br />

Labor Cost ($)<br />

VSD and Controls 1 $9,600.00 $9,840 $1,391.25 $1,560<br />

Premium Efficiency Motor 1 $1,225.00 $1,256 $80.00<br />

$90<br />

City: <strong>Los</strong> <strong>Angeles</strong><br />

City Index Material Multiplier:<br />

City Index Labor Multiplier:<br />

102.5%<br />

112.1%<br />

Raw Costs:<br />

Sales Tax: 8.25%<br />

Contractor O&P: 12.00%<br />

Subtotals:<br />

Contingency:<br />

Engineering:<br />

Construction Phase:<br />

Project Management:<br />

10.00%<br />

15.00%<br />

5.00%<br />

6.00%<br />

$11,096 $1,649<br />

$915<br />

$1,441<br />

$13,452<br />

$1,345<br />

$2,524<br />

$841<br />

$1,010<br />

N/A<br />

$198<br />

$1,847<br />

$185<br />

Totals: $14,798 $2,032<br />

Total Project Cost: $21,205<br />

Project Economic Summary, Including Cogeneration and Purchased Utility Impacts<br />

Total Project Cost: $21,205<br />

Rebate/Incentive*:<br />

$8,834<br />

Net Project Cost: $12,371<br />

Net Simple Payback Period (yrs): 3.8<br />

Total Purchased Electricity Savings (kWh/yr):<br />

Total Purchased Gas Savings (th/yr):<br />

Total Purchased Annual Cost Savings ($/yr):<br />

*Highlighted incentives have been capped at 80% of the total project cost. It is recommended that these projects be bundled together with other projects to maximize<br />

incentive funding.<br />

36,809<br />

0<br />

$3,239<br />