Technology Centre Systems Program – <strong>Draft</strong> DPR for New TC at Rohtak<br />

Expenditure pattern<br />

Capital expenditure<br />

Total capital expenditure will be to the tune of around INR 128.7 Crore for setting up of new TC at<br />

Rohtak. Summary of the Capital Expenditure is provided as below:<br />

Table 36: Capital expenditure<br />

Capex( Inc. Contingency @5%)<br />

Cost (INR Lakhs)<br />

Production Machinery and equipment 1,228<br />

Training machines and equipment 2,735<br />

Building and construction 8,224<br />

Other infrastructure 425<br />

Pre-Operative Expenses 258<br />

Total Capex including contingency 12,870<br />

Plant and machinery<br />

Total expenditure on machines to the tune of around INR 3,963 lakhs is envisaged for the setting up<br />

of new TC at Rohtak.<br />

Table 37: Plant & Machinery<br />

Capex<br />

INR Lakhs<br />

Total Plant and Machinery including Contingency @ 5% of capex 3,963<br />

The capital cost estimate for the proposed modernisation project has been prepared jointly by O/o<br />

DC-MSME and EY team based on inputs from the following:<br />

► Technology workshop at Bhubaneswar; 2 day detailed sessions led by Dr. Clive Hickman on<br />

‘Future Manufacturing Technology Trends’,<br />

► Market opportunity assessment by EY team<br />

► Validation of technology needs by detailed discussions and site visits to key manufacturing<br />

organisations<br />

► Site visits and discussions with local industry and industry associations.<br />

► Inputs from Office of DC MSME<br />

► Inputs as per the World Bank Environment and Safety requirements<br />