Technology Centre Systems Program – <strong>Draft</strong> DPR for New TC at Rohtak<br />
Clearances required and respective authorities<br />
The proposed TC at Rohtak is one of the first Greenfield projects proposed under TCSP. This would<br />
include development of physical infrastructure including facilities like production, training,<br />
administration, hostel, canteen, utilities etc. keeping in view the long-term sustainability. The same<br />
would require clearances at different levels during construction such as approval of layout plan,<br />
environmental clearance, electricity and water supply connection, health and safety clearance and<br />
other associated clearances. Obtaining these clearances would be crucial for timely completion of<br />
the project and therefore needs to be planned well in advance. The following table gives indicative<br />
details of the various clearances along with the respective approving authorities and the tentative<br />
time required. However, considering that land has already been allotted to O/o DC-MSME for<br />
development of TC, some of these regulations may not be applicable.<br />
Table 16: Clearances required and respective authorities<br />
S. No<br />
1.<br />
2.<br />
3.<br />
4.<br />
Required<br />
clearance/<br />
approvals 34<br />
Registration under<br />
VAT Act<br />
Registration under<br />
CST Act<br />
Tax Clearance<br />
Certificate<br />
Land conversion -<br />
Conversion of land<br />
use<br />
Department /agency<br />
Commercial Taxes<br />
Department<br />
Commercial Taxes<br />
Department<br />
Commercial Taxes<br />
Department<br />
Revenue Department<br />
5. Land Allotment Revenue Department<br />
6.<br />
7.<br />
8.<br />
Allotment of plots in<br />
Industrial Areas<br />
Issue of NOC to the<br />
authority concerned<br />
regarding<br />
conversion of land<br />
use<br />
Environmental<br />
Clearance (Consent<br />
of Air and Water<br />
Pollution)<br />
HSIIDC/ State<br />
department<br />
HSIIDC/ State<br />
department<br />
Ministry of<br />
Environment and<br />
Forests<br />
Tentative time limit for approval<br />
24 hours<br />
24 hours<br />
(days)<br />
1 day in case of non-default of tax<br />
payment<br />
30 days for up to 10 hectares<br />
60 days for above 10 hectares<br />
30 days if allotment is to be made at<br />
the District Level<br />
60 days in case Government's<br />
approval is required<br />
30 days<br />
15 days<br />
Site/environment clearance: 90<br />
days,<br />
NOC to establish: 45 days,<br />
34<br />
Indicative list of clearances/ approvals<br />
Technology Centre Systems Program – DPR for New TC at Rohtak 92