12. Filing drums for disposal in Arkhangelsk.<br />

During the work, the drum with a mini-tractor with a cart going to the work area number 1 of<br />

technological platforms.<br />

When collecting drum zone number 1 autopsy was performed tube drum in order to determine in<br />

her presence and the approximate volume of process fluid (probe).<br />

In the case of presence in a vat of liquid phase fluid, it is using the truck passed into the zone<br />

number 2 for the rapid analysis of liquids for the presence of PCB compounds and the<br />

subsequent opening of the bottom, after emptying the drums, in the absence of such<br />

contaminants.<br />

In the absence of the presence of PCB compounds in drums made the following operations:<br />

- To be destroyed if a drum was filled with more than 2 / 3 of its volume, it is transported by<br />

truck to tanks where the process of pumping the liquid in the tank. Pumping of liquids carried<br />

out by a pump Grundof.<br />

- If the discarded drum was filled in less than 2 / 3 of its volume, it passed into the zone number<br />

3 for the burning of residues on the setting Fakel-1M, followed by compaction by the press.<br />

In that case, if drum was solid phase (ice), it is by truck passed in the technological unit for prethawing.<br />

After thawing samples and proximate analysis was carried out in accordance with the<br />

method described above.<br />

If the drum was empty and did not contain any technical liquids, was passed on to the<br />

compaction press.<br />

Drums of detecting signs of PCB compounds were marked with white paint and dumped on a<br />

separate site.<br />

Thus, the organization of technological process in the area number 3 is carried out in two<br />

streams:<br />

stream of drums to be sent to the compaction (initial empty drums, empty drums after removing<br />

remnants of technical liquids and washing);<br />

stream of drums to be sent to a preliminary roasting, followed by compaction (drums filled with<br />

less than 2 / 3 of the volume in the absence of their PCB waste).<br />

After the implementation of the firing and compacting drums held their storage. Pressed for<br />

storage casks used two platforms. First on the shore of the bay, about 300 m ESE from the work<br />

site, the second in the 100 - 130 m to the ESE of the construction site. On the first landing<br />

compacted drums were filled with three wooden, metal containers that are convenient for the<br />

subsequent transport of the drums on the ship. A total of 130 containers were placed in drums.<br />

The second site was chosen near the job site, on the horizontal section on the windward side. On<br />

this site had been stored 870 drums. These drums were tied with wire in bundles, 14 - 17 pieces<br />

for ease of onward transport.<br />

In carrying out the work in the area number 1 it was found that of 1,238 drums of selected about<br />

87 pieces have been partially filled with kerosene, about 78 pieces - diesel fuel. Drums<br />

containing the remains of gasoline, was not. Drums of gasoline were under a dry and empty, or<br />

full of holes and the remnants of only water.<br />

The number of drums, containing PCB-waste, was 8 pieces.<br />

FINAL REPORT for Contract No. CS-NPA-Arctic-13/2009 of December 01, 2009 within the framework of pilot project Development<br />

of Technology of clean up of the area of Decommissioned Sites of The Russian Federation Ministry of Defense in the Arctic by the<br />

Example of Alexanra Island of Franz Josef Land Archipelago from Hazardous Waste<br />