4. 9. Transportation/Circulation<br />

The traffic study conducted as part <strong>of</strong> the Redevelopment Plan FEIR assumes that the<br />

project site develops as Restricted Industrial use to an FAR <strong>of</strong> 0.75. Given the site area <strong>of</strong><br />

12.21 acres per County Assessor records (not including the proposed quitclaim <strong>of</strong> the Victory<br />

Truck Boulevard easement), it is estimated that the Redevelopment Plan FEIR traffic study<br />

includes development <strong>of</strong> about 398,900 square feet <strong>of</strong> Restricted Industrial uses on the project<br />

site.<br />

Using the trip generation rates published in the Redevelopment Plan FEIR, Table 13 on<br />

page 77, indicates that this level <strong>of</strong> development would generate approximately 365 trips during<br />

the A.M. peak hour and 390 trips during the P.M. peak hour. These trips were distributed<br />

across the street system using distribution patterns from the Redevelopment Plan FEIR, and<br />

were subtracted from the Year 2010 base traffic forecasts to represent Year 2010 volumes<br />

without any development on the project site.<br />

The projected Year 2010 cumulative base traffic volumes at the eleven study<br />

intersections are included in Appendix C. These forecasts represent projected conditions at<br />

Year 2010 with development under the provisions <strong>of</strong> the Redevelopment Plan throughout the<br />

Redevelopment Plan area,· but without any development on the project site.<br />

Levels <strong>of</strong> Service and Mitigation Measures<br />

The Year 2010 cumulative base traffic forecasts were analyzed to detennined the<br />

projected future peak hour levels <strong>of</strong> service at the eleven study intersections, without any<br />

development on the project site and without consideration <strong>of</strong> the mitigation measures proposed<br />

in the Redevelopment Plan FEIR. Table 14 on page 78, summarizes the results <strong>of</strong> this analysis.<br />

As can be seen in Table 14, four <strong>of</strong> the intersections (Flower Street/Western Avenue,<br />

San Fernando Road/Sonora Avenue, San Fernando Road/Grandview Avenue, and San Fernando<br />

Road/Doran Street) are projected to operate at poor levels <strong>of</strong> service <strong>of</strong> E or F during one or<br />

both <strong>of</strong> the A.M. and P.M. peak hours under Year 2010 conditions with development throughout<br />

the Redevelopment Plan area but with no development on the project site.<br />

The Redevelopment Plan FEIR proposed mitigation measures at three <strong>of</strong> these locations<br />

to mitigate Year 2027 conditions. An analysis was conducted to detennine what components<br />

<strong>of</strong> the Redevelopment Plan FEIR mitigation program would need to be implemented to mitigate<br />

the Redevelopment Plan traffic impacts at 2010 with no development on the project site. The<br />

Planning ConsulranlS Research<br />

<strong>Glendale</strong> Redenlopment Agency<br />

Page 76<br />

DreamWorks Animation Campus Addeadum EJR<br />

June 1996