TIP<br />
To change a task from a subtask to a summary task or to change its level in <strong>the</strong> WBS, you can “outdent”<br />
<strong>the</strong> task. To outdent <strong>the</strong> task, click <strong>the</strong> cell of <strong>the</strong> task or tasks you want to change, and <strong>the</strong>n click<br />
<strong>the</strong> Outdent button on <strong>the</strong> Formatting toolbar. Remember, <strong>the</strong> tasks in <strong>Project</strong> 2007 should be entered<br />
in an appropriate WBS <strong>for</strong>mat with several levels in <strong>the</strong> hierarchy.<br />
Numbering Tasks<br />
Depending on how <strong>Project</strong> 2007 is set up on your computer, you may or may not see numbers<br />
associated with tasks as you enter and indent <strong>the</strong>m.<br />
To display automatic numbering of tasks using <strong>the</strong> standard tabular numbering system<br />
<strong>for</strong> a WBS:<br />
Outline<br />
numbers<br />
show WBS<br />
hierarchy<br />
Show<br />
outline<br />
number<br />
check box<br />
1. Display <strong>the</strong> Options dialog box. Click Tools on <strong>the</strong> Menu bar, and <strong>the</strong>n click<br />
Options. The Options dialog box opens.<br />
2. Show outline numbers. Click <strong>the</strong> View tab, if necessary. Check Show outline<br />
number in <strong>the</strong> “Outline options <strong>for</strong> <strong>Project</strong>1” section of <strong>the</strong> View tab. Click OK<br />
to close <strong>the</strong> dialog box. Figure A-22 shows <strong>the</strong> Options dialog box and resulting<br />
outline numbers applied to <strong>the</strong> WBS tasks.<br />
FIGURE A-22 Adding Outline Numbers<br />
Saving <strong>Project</strong> Files With or Without a Baseline<br />
An important part of project management is tracking per<strong>for</strong>mance against a baseline, or<br />
approved plan. <strong>Project</strong> 2007 does not prompt you to save a file with or without a baseline<br />
each time you save it, as some previous versions did. The default is to save without a<br />
baseline. It is important to wait until you are ready to save your file with a baseline because<br />
<strong>Project</strong> 2007 will show changes against a baseline. Since you are still developing your<br />