Appendix A<br />

2. Open <strong>the</strong> Resource Leveling dialog box. Click Tools on <strong>the</strong> Menu bar, and <strong>the</strong>n<br />

click Level Resources. The Resource Leveling dialog box opens, as shown in<br />

Figure A-60. Uncheck <strong>the</strong> Level only within available slack option, if necessary.<br />

Uncheck Level only<br />

within available slack,<br />

if needed<br />

FIGURE A-60 Resource Leveling Dialog Box<br />

3. Level <strong>the</strong> file and review <strong>the</strong> date changes. Click <strong>the</strong> Level Now button. In this<br />

example, resource leveling moved <strong>the</strong> project completion date from 11/16 to<br />

11/19, as shown on <strong>the</strong> Gantt chart milestone symbol <strong>for</strong> Task 42, <strong>Project</strong><br />

completed. Also notice that <strong>Project</strong> 2007 automatically highlighted <strong>the</strong> cells<br />

that were affected by this change.<br />

4. View Kathy’s Resource Graph again. Click <strong>the</strong> Resource Graph button on<br />

<strong>the</strong> View Bar. If necessary, use <strong>the</strong> scroll bar in <strong>the</strong> resource histogram pane<br />

to display June 2009. Notice that Kathy is still overallocated in June 2009.<br />

5. Level using <strong>the</strong> Hour by Hour option. Click Tools on <strong>the</strong> Menu bar, and <strong>the</strong>n<br />

click Level Resources. Change <strong>the</strong> basis <strong>for</strong> leveling from Day by Day to Hour<br />

by Hour, click <strong>the</strong> Level Now button, keep <strong>the</strong> default option of Entire pool<br />

in <strong>the</strong> Level Now dialog box, and <strong>the</strong>n click OK. Notice that Kathy’s overallocation<br />

disappears. Double-click <strong>the</strong> right scroll arrow in <strong>the</strong> resource name<br />

pane to reveal in<strong>for</strong>mation about Mary. Remember that <strong>the</strong> left pane displays<br />

different resources, and <strong>the</strong> right pane reveals <strong>the</strong> resource histogram over<br />

time. Mary’s overallocations are also gone because of this resource leveling.<br />

6. View <strong>the</strong> Gantt chart again. Click <strong>the</strong> Gantt Chart button on <strong>the</strong> View Bar<br />

and move <strong>the</strong> split bar to review <strong>the</strong> Gantt chart, if necessary. The project<br />

completion date has been moved back to 11/23 because of <strong>the</strong> resource<br />

leveling.<br />

7. View <strong>the</strong> Leveling Gantt chart. Click View on <strong>the</strong> Menu bar, click More Views,<br />

and <strong>the</strong>n double-click Leveling Gantt. Click <strong>the</strong> Zoom Out button to adjust<br />

<strong>the</strong> timescale to show months and weeks, and scroll to <strong>the</strong> right in <strong>the</strong> Gantt<br />

Copyright 2009 Cengage Learning. All Rights Reserved.<br />

May not be copied, scanned, or duplicated, in whole or in part.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!