505.3.2 Equipment : A mechanical broom, compressor, self propelled or trailed bitumen<br />

heater/distributor, mechanical aggregates spreader and 8 to 10 tonnes smooth steel wheel roller<br />

or vibrating roller are required for the preparation of penetration macadam.<br />

505.3.3 Preparation of the base: same as per clause 504.3.2 and 504.3.3.<br />

505.3.4. Spreading coarse aggregates:<br />

(i)The coarse aggregate shall be dry and clean and free from dust, and shall be spread uniformly<br />

and evenly at the rate specified in Table 500-6.<br />

(ii)It shall be spread by a self- propelled or tipper tail mounted aggregate spreader capable of<br />

spreading aggregate uniformly at the specified rates over the required widths.<br />

(iii)The surface of the layer shall be carefully checked with camber templates to ensure correct<br />

line and level and cross fall.<br />

(iv)The spreading shall be carried out such that the rolling and penetrating operations can be<br />

completed on the same day.<br />

(v)Segregated aggregates or aggregates contaminated with foreign material shall be removed<br />

and replaced.<br />

505.3.5. Compaction: After the spreading of coarse aggregates, dry rolling shall be carried out<br />

with an 8 — 10 tonne smooth steel wheel roller. The requirements given in Clause 501.6 and<br />

501.7 shall apply. After initial dry rolling, the surface shall be checked with a crown template and<br />

a 3 meter straight-edge. The surface shall not vary more than 10 mm from die template or<br />

straight-edge. All surface irregularities exceeding the above limit shall be corrected by removing<br />

or adding aggregates as required. The rolling shall continue until the compacted coarse<br />

aggregate has a firm surface true to the cross section shown on the plans and has a texture that<br />

will allow free and uniform penetration of the bituminous material.<br />

505.3.6. Application of bituminous material: After the coarse aggregate has been rolled and<br />

checked, the bituminous binder shall be applied, at the rate given in Table 500-6, in accordance<br />

with Clause SOI, and at a temperature directed by the Engineer in charge. At the time of applying<br />

the binder, the aggregates shall be surface dry for the full depth of the layer.<br />

505.3.7. Application of key aggregates: The key aggregate shall be clean dry and free from<br />

dust. Immediately after the first application of bitumen, the key aggregates shall be spread<br />

uniformly over the surface by means of an approved mechanical spreader or by approved manual<br />

methods at the rate specified in Table 500-6. Where directed by the Engineer in charge, the<br />

surface shall be swept and the quantity of key aggregate adjusted to ensure uniform application,<br />

with all the surface voids in the coarse aggregate being filled without excess. The entire surface<br />

shall then be rolled with a 8 - 10 tonnes smooth steel wheel roller (or vibrating roller operating in<br />

non -vibratory mode) in accordance with the procedure specified in Clause 505.3.5.<br />

505.4. Surface Finish and Quality Control<br />

The surface finish of the completed construction shall conform to the requirements of Clause 902.<br />

For control of the quality of materials supplied and the works carried out the relevant provisions of<br />

Section 900 shall apply.<br />

505.5. Surfacing<br />

The Penetration Macadam shall be provided with a surfacing (binder/ wearing course) within a<br />

maximum of forty-eight hours. If there is to be any delay, the penetration macadam shall be<br />

covered by a seal coat before opening to traffic. The seal coat in such cases shall be considered<br />

incidental to the work and shall not be paid for separately.<br />

505.6. Arrangements for Traffic<br />

During the period of construction, arrangements for traffic shall be made as directed by the<br />

Engineer in charge.